BILL ANALYSIS                                                                                                                                                                                                    



                                                                    SB 1388
                                                                    Page  1

          Date of Hearing:  June 19, 2000

                      ASSEMBLY COMMITTEE ON NATURAL RESOURCES 
                                 Howard Wayne, Chair
                     SB 1388 (Peace) - As Amended:  May 16, 2000

           SENATE VOTE  :  39-0
           
          SUBJECT  :  Electrical power facilities.

           SUMMARY  :  This bill enacts California Energy Commission (CEC)  
          recommended changes to current electrical power plant siting  
          processes.  The bill also makes several changes to continued  
          implementation of electrical restructuring in California.

           EXISTING LAW  : 

          1)Provides the CEC with authority over licensing of power plants  
            in California.

          1)Provides certain state and local agencies with advisory  
            responsibilities to the CEC during the power plant siting  
            process.
           
          1)Requires the CEC to prepare a geothermal resource sufficiency  
            study whenever it considers a proposal to site a geothermal  
            electrical generation facility.

          1)Provides the Federal Energy Regulatory Commission (FERC) with  
            the authority to set electric transmission rates.

          1)Provides for competition in the generation and sale of  
            electricity.

           THIS BILL  :

          1)Requires local agencies that provide recommendations on power  
            plant sitings to the CEC to do so within 180 days.

          1)Eliminates the requirement that the CEC prepare a geothermal  
            resource sufficiency study whenever it considers a proposal to  
            site geothermal electrical generation facilities.

          1)Requires the California Public Utilities Commission (CPUC), in  
            conjunction with the Electrical Oversight Board, to facilitate  








                                                                    SB 1388
                                                                    Page  2

            approval of reasonable transmission facility planning and  
            engineering procedures.

          1)Requires the CPUC to conduct specified pilot projects of  
            certain customers to gauge small consumer responsiveness to  
            energy usage and price information.

           FISCAL EFFECT  :  According to the Senate Appropriations  
          Committee, the bill would have negligible costs.



           COMMENTS  :

           1)Background
           
          This bill contains three main sections:  the first reflecting  
          recent recommendations by the CEC, the second attempting to  
          address the issue of the need for better responsiveness to  
          residential and small commercial electricity customers, and the  
          third to generally help ensure that electrical corporations  
          continue developing plans to improve the functioning of the  
          current electrical transmission system.

          The second and third sections of the bill are not within the  
          jurisdiction of this committee.  Those sections should be  
          addressed in the Assembly Committee on Utilities and Commerce to  
          which this bill has been referred following this committee.  

          2)   180 Days
           
          The first section of the bill, reflecting the addition of the  
          180 day requirement for comments on the power plant siting  
          process and the deletion of the geothermal sufficiency study are  
          both recommendations of the CEC, based on a recent report  
          released in March, 2000 on changes to the electric industry.  

          According to the author's office, the current power plant siting  
          process takes about 12 months, and in order for comments from  
          local and state agencies to be accommodated in the process, a  
          time limit is necessary.  Thus, a compromise of 180 days was  
          recommended by the CEC.

          3)   Geothermal resource sufficiency studies
           








                                                                    SB 1388
                                                                    Page  3

          Geothermal projects in California are generally electrical  
          generation projects that use underground heat and steam as their  
          energy source.  A resource sufficiency study, required by  
          current law, analyzes whether there is enough underground heat  
          and steam to power the plant through its projected life.  In its  
          recent report, the CEC recommended deleting this requirement  
          because in a competitive generation market, it believes the  
          responsibility of ensuring an adequate fuel supply should fall  
          to the power plant developer and not with the CEC.

           REGISTERED SUPPORT / OPPOSITION  :

           Support  

          None on file
           
          Opposition  

          None on file


           Analysis Prepared by  :  Kyra Emanuels / NAT. RES. / (916)  
          319-2092