BILL ANALYSIS                                                                                                                                                                                                              1





                SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE
                               DEBRA BOWEN, CHAIRWOMAN
          

          SB 1388 -  Peace                                  Hearing Date:   
          May 9, 2000                S
          As Amended:         May 4, 2000              FISCAL       B

                                                                        1
                                                                        3
                                                                        8
                                                                        8


                                      DESCRIPTION
           
           Current law  provides the California Energy Commission (CEC) with  
          responsibility for licensing large power plants.  Certain state  
          and local agencies have advisory responsibilities to the CEC  
          under particular circumstances. 

           This bill  requires those state and local agencies to provide  
          recommendations within 180 days of the filing of an application  
          to license a power plant.

           Current law  requires the CEC to prepare a geothermal resource  
          sufficiency study whenever it considers a proposal to site a  
          geothermal electric generation facility.

           This bill  deletes that requirement.

           Current law provides the Federal Energy Regulatory Commission  
          (FERC) with authority to set electric transmission rates.

           This bill  requires the CPUC, in conjunction with the Electricity  
          Oversight Board (EOB), to facilitate FERC approval of reasonable  
          transmission facility planning and engineering expenditures,  
          even if those expenditures do not result in operational  
          transmission facilities.  This bill further requires the CPUC to  
          approve all reasonable transmission planning, design, and  
          engineering expenditures irrespective of whether those  
          expenditures result in an operational transmission line.

           Current law  provides for competition in the generation and sale  











          of electricity.

           This bill  requires the California Public Utilities Commission  
          (CPUC) to conduct specified pilot projects to gauge small  
          consumer responsiveness to energy usage and price information.

















































                                      BACKGROUND
           
          This bill has three distinct parts:  Part 1 deals with power  
          plant licensing improvements recommended by the CEC, Part 2  
          deals with recovering transmission planning costs from  
          customers, and Part 3 establishes pilot programs to test small  
          customer responsiveness to energy price and usage information.

           Part 1 - CEC Report Recommendations
           
          In March 2000, the CEC issued a report recommending a number of  
          improvements to its power plant siting process.  That report,  
          which was reviewed by this Committee during an April 11, 2000,  
          informational hearing, suggests a number of statutory,  
          regulatory, and management changes.  

          This bill implements two of the CEC's recommended statutory  
          changes, the first of which deletes the requirement that the CEC  
          perform a steam-field adequacy analysis for geothermal projects.  
           Geothermal projects are electrical generation projects which  
          utilize underground heat and steam as the energy source (e.g.  
          the Geysers power plants).  A steam-field adequacy analysis  
          investigates whether there is enough underground heat and steam  
          to power the plant through its projected life.  The CEC  
          recommended deleting this requirement because in a competitive  
          generation market, it believes the responsibility of ensuring an  
          adequate fuel supply, in this case heat and water, should fall  
          to the power plant developer and not rest with the CEC. 

          The second of the recommended changes implemented by this bill  
          is a requirement that state and local governmental entities  
          having jurisdiction or an interest in a proposed power plant  
          make their recommendations within 180 days of the filing of the  
          project.  The CEC noted that it has a statutory one year  
          requirement to process power plant siting applications and its  
          ability to meet that deadline is jeopardized in cases where  
          state and local agencies provide their comments late in the  
          process.  While the CEC has entered into Memoranda of  
          Understanding (MOU) with the California Air Resources Board, the  
          Department of Toxic Substance Control, the California  
          Independent System Operator, and a number of other agencies to  
          establish a 180 day target for input, this bill applies a  
          statutory requirement of 180 days to those agencies and to other  
          entities not covered by such MOUs.












           Part 2 - Transmission Lines

           Transmission lines are an essential electric infrastructure and  
          those lines owned by investor-owned electric utilities (IOU),  
          such as PG&E and Southern California Edison, are rate regulated.  
           The IOUs plan and engineer new transmission lines to serve  
          their service territories, but they can't build those lines  
          without approval from the Independent System Operator (ISO), the  
          statutorily-created entity controlling the transmission system.   
          The ISO evaluates all transmission facility proposals and  
          considers alternate ways of meeting customer demand, such as  
          building new power plants or alternative transmission  
          facilities, then selects the least costly option.

          IOUs are concerned that if their transmission facilities aren't  
          permitted to be built, they aren't assured that their planning  
          and engineering costs for transmission facilities will be  
          recoverable from customers.  The failure to be able to recover  
          those costs could discourage utilities from doing necessary  
          planning, thereby impairing the future ability of the  
          transmission system to operate reliably and efficiently.  
































          This bill proposes to resolve that concern by stating that the  
          Legislature finds that reasonable expenditures for planning and  
          engineering of transmission facilities is in the public interest  
          and requires the CPUC and the EOB to jointly facilitate approval  
          of those costs in the transmission rates approved by FERC.  The  
          bill further requires the CPUC to allow recovery of all  
          reasonable expenditures for transmission planning, design, and  
          engineering, regardless of whether such facilities become  
          operational.

           Part 3 - Residential and Small Commercial Customer Pilot  
          Projects
           
          Much of the effort in restructuring the electric industry was  
          focused on creating a competitive market for electric generation  
          - in other words, increasing the supply of electricity - but  
          little work was done on addressing the issue of consumer demand,  
          largely because the price for electricity was frozen.  

          As electric rates are unfrozen, which is the case in the San  
          Diego Gas & Electric Company (SDG&E) territory, customers will  
          see variations in their electric bill based not just on changes  
          in usage but also on changes in the price of electricity.  While  
          rates were frozen, consumers had little incentive to pay  
          attention to  when  they were using electricity because the price  
          for electricity was always the same.  As rates become unfrozen,  
          consumers who want to keep their bills low have an incentive to  
          use their electricity at the least expensive times of the day -  
          if they can easily figure out the price of electricity at a  
          given time of day and if they are charged a price which varies  
          by time of day.  

          The author believes this consumer reaction, known as "demand  
          responsiveness," is an important component of electric system  
          reliability and of a well-functioning market.  Encouraging  
          demand responsiveness is particularly critical at a time when  
          California is facing a squeeze in resources and the prospect of  
          high energy prices under adverse climatic conditions.

          This bill establishes three pilot projects limited to  
          residential and small commercial customers to test varying ways  
          of providing consumers with that type of pricing information.   
          The first provides real-time (minute-to-minute)  usage  
          information  ; the second provides for peak, mid-peak, and  











          off-peak  usage and rate information  coupled with a utility rate  
          schedule that differentially prices electricity at peak,  
          mid-peak and off-peak rates, while the third provides for hourly  
           usage and rate information  coupled with a utility rate schedule  
          that allows prices to vary by the hour.  The author believes  
          obtaining a better understanding of the extent to which various  
          levels and types of usage and price information will trigger  
          demand responsiveness is essential in understanding the cost  
          effectiveness of the types of investments and opportunities that  
          should be afforded customers.

          The bill requires all utilities that no longer have frozen rates  
          to participate in the three pilots, which means only SDG&E will  
          be immediately affected by the bill.  However, once Pacific Gas  
          & Electric Company (PG&E) and Southern California Edison (SCE)  
          are out from the rate freeze (which should happen sometime in  
          2001), then some of their customers will also have to  
          participate in the three pilot programs.




































          The total pilot program participation is limited to 3% of the  
          residential and small commercial customers of each utility and  
          is further limited to the minimum number of customers needed to  
          develop a statistically valid sample for the two pilots with  
          time-of-use rates.  The design and implementation of the pilot  
          study shall include interested energy service providers and  
          equipment manufacturers.

          Each of the three pilot programs is required to use a standard  
          usage information output interface, which the bills defines, and  
          the CPUC will select the interface that conforms with nationally  
          recognized standards.  This bill requires that the interface be  
          secure, safe, and the most cost-effective available. The purpose  
          of a standard usage information output interface is to establish  
          an industry standard, which in turn will drive the creation of  
          compatible devices which use that consumer information

          The cost of the pilot programs is recoverable from customers.

                                     KEY QUESTIONS
           
          1.Does requiring state and local agencies to comment on power  
            plant siting proposals within 180 days provide them with  
            adequate time to prepare comments?

          2.Should the CPUC and the EOB be required to facilitate approval  
            of utility transmission planning costs in the overall  
            transmission rates approved by FERC?

          3.Are the pilot programs created by this bill adequate and  
            necessary for determining consumer demand responsiveness?

                                       COMMENTS
           
          1)  Timeline For Input  .  As noted in Part 1 of the "Background"  
            section, the CEC is required to process power plant siting  
            applications within a year of receiving a completed  
            application and its ability to meet that deadline is  
            jeopardized in cases where state and local agencies provide  
            their comments late in the process.  To alleviate that  
            problem, this bill requires state and local governmental  
            entities having jurisdiction or an interest in a proposed  
            power plant to make their recommendations within 180 days of  
            the filing of the project.  












          2)  Transmission Planning Cost Recovery  .  As noted in Part 2 of  
            the "Background" section, this bill requires the CPUC and the  
            EOB to facilitate FERC approval of reasonable transmission  
            facility planning and engineering expenses - even if those  
            expenditures don't result in operational transmission  
            facilities.  

            The author believes electrical corporations shouldn't be  
            discouraged from engaging in transmission planning because of  
            concerns that the costs of such planning may not be recovered  
            in the event that the project isn't ultimately needed.  FERC's  
            practice is to allow recovery of only 50% of such costs.  By  
            directing the CPUC and EOB to essentially go to bat for the  
            utilities at FERC, the author hopes to clearly express  
            California's policy preferences to FERC and to persuade the  
            agency to allow for more than 50% cost recovery.  To more  
            clearly accomplish this goal,  the author and committee may  
            wish to make two clarifications  :  



































               The first sentence of paragraph (b) of this section (Page  
               17, Line 13) seems to inadvertently require the CPUC to  
               allow for cost recovery of all transmission planning  
               expenditures even if they're denied by the FERC.  This  
               doesn't seem to be the intent of the overall provision and  
                the author and committee may wish to consider  clarifying  
               this line.  

               Second, while the first paragraph of this provision (Page  
               17, Line 3) allows "reasonable" expenditures to be deemed  
               prudent and be recoverable, that same terminology isn't  
               carried over to the second paragraph.  The term  
               "reasonable" is important because it implies a CPUC review  
               and allows for obviously inappropriate expenditures to be  
               excluded.   The author and committee may wish to consider   
               inserting the term "reasonable" on Page 17, Line 23.

          3)  Timing of Pilot Projects  .  The bill requires all investor  
            owned utilities to establish these pilot programs within 15  
            months of the date at which their customers are out of the  
            rate freeze.  For SDG&E, that means it will be required to set  
            up such a program within 15 months of the enactment of this  
            bill, which will be January 1, 2001.  However, since PG&E and  
            SCE may not end their rate freeze until late 2001, it could be  
            two years between the time when the SDG&E pilot projects begin  
            and the PG&E and SCE projects get off the ground.

            The bill requires all of the pilot projects to have identical  
            offerings so the results of the pilots can be easily compared.  
             However, given the potentially long time interval between  
            pilots, there may be changes in technology or practice - or  
            useful results from the first pilots - that the author may  
            wish to incorporate into the second set of pilot projects.  As  
            such,  the author and committee may wish to consider  giving the  
            CPUC the authority to adjust or waive the additional pilot  
            programs if it doesn't feel their implementation is warranted.

          4)  Size of Pilot Projects  .  The pilot project in each area is  
            limited to 3% of the residential and small commercial  
            customers of each utility, and two of the three programs  
            within each project are capped at the minimum number of  
            customers needed to develop a statistically valid sample.   The  
            author and committee may wish to consider  clarifying that the  
            3% figure applies to the total aggregate number of customers  











            taking part in all three pilot programs. 

          5)  Cost of Pilot Projects  .  Under this bill, the utilities would  
            select the residential and small customers to take part in the  
            pilot project and the cost of the project would be recovered  
            in the rates spread across the entire rate base, including  
            both small and large customers.

            According to information provided by the author's office, the  
            standard usage information output interface required by the  
            bill costs about $35 per customer, though that doesn't include  
            the cost of the visual display device in the home or the  
            connection from that display device to the output interface.   
            If the total equipment cost is, for example, $70 per home and  
            SDG&E includes 3% of its total residential and small customer  
            base in the program, the total cost of the pilot in the SDG&E  
            territory could approach $2.5 million, though other estimates  
            (based on a $200 equipment cost) have been as high as $7  
            million..

            If the total cost of the project is of concern,  the author and  
            committee may wish to consider  limiting participation in each  
            of the three programs to no more than the minimum number of  
            people necessary to provide a statistically valid sample.   
            Currently in the bill, this limitation is imposed on the  
            second and third pilot projects, but not on the first (Page  
            13, Lines 33-36).



























          6)  Display Error  .  Providing customers with easily accessed  
            information is a cornerstone to a sound test of demand  
            responsiveness, but two of the pilot projects inadvertently  
            exclude a visual display capability.  The author and committee  
            may wish to consider  correcting this drafting error by  
            deleting the prohibition of the visual display module in two  
            of the pilot projects and instead requiring them to have a  
            visual display module (Page 12, Line 30 and Page 12, Line 40).

          7)  Rate Schedules  .  Under the electric restructuring statutes,  
            electric utilities simply pass through their cost of acquiring  
            electricity.  This bill contemplates the utility establishing  
            "rate schedules" which aren't necessarily limited to cost  
            pass-throughs and which may require some averaging by the  
            utility.   The author and committee may wish to consider  
             clarifying that the utility rate schedules adopted pursuant to  
            this bill are subject to CPUC approval and should reflect the  
            utility's actual energy costs for the relevant time intervals.  
             This could be accomplished by making the following changes:   
            Page 12, Line 26, before "Electrical corporations" add  
            "Subject to commission approval,"; Page 12, Line 28, after  
            "use" add "that reflects the electrical corporation's actual  
            energy cost"; Page 12, Line 34, before "Electrical  
            corporations" add "Subject to commission approval,";  Page 12,  
            Line 36,  delete "net"; and Page 12, Line 37, end the sentence  
            after "cost" and delete the remainder of the sentence.

          8)  Customer Participation  .  Two of the pilot projects created by  
            this bill involve changing rate schedules.  Residential and  
            small-commercial customers typically have rates which don't  
            vary by time or season.  Under two of the pilot projects, the  
            customers will have rates which vary by time of day and time  
            of year, and they'll have timely information as to how those  
            rates are changing.  This is a significant change for  
            customers which may or may not be welcome by all.   The author  
            and committee may wish to consider  how customers are selected  
            for the pilot projects.  Should the utility be able to select  
            the customers or should customers be able to volunteer to  
            participate?  In the event the utility selects the customers,  
            should those customers be able to "opt out' of participating?   


          9)  Interpreting The Results of The Pilot Projects  .  The pilot  
            studies are intended to answer basic questions about small  











            customer demand responsiveness, including whether any  
            behavioral changes justify wide scale implementation of these  
            programs.  In a competitive electric market, this data may  
            have value to other potential providers of services and it  
            would seem to be in keeping with the spirit of the bill to  
            make this information widely available.  While the bill  
            requires a report to the Legislature on the study  results  ,  the  
            author and committee may wish to consider  making the study  
             data  publicly available, subject to sufficient confidentiality  
            of individual customer information.

          10)                                 Technically Speaking  .  The  
            author may wish to consider the following technical amendments  
            to the measure: 

               a) Page 5, Line 32:  After "is" insert "not"
               b) Page 5, Line 34:  Replace "is" with "may be" 
               c) Page 6, Line 31:  Before "Expenditures" insert  
               "Reasonable"
               d) Page 6, Line 34:  After "interest" delete ", reasonable  
               and" and insert "and are deemed" 
               e) Page 11, Line 40:  Replace "(c)" with "(a)" 
               f) Page 12, Line 20:  After "customer" insert ", electrical  
               corporation,"
               g) Page 14 Line 18: Replace "(c)" with "(a)"





























                                       POSITIONS
           
           Sponsor:  
          Author

           Support:
           Sempra Energy

           Oppose:
           California Manufacturers & Technology Association


          Randy Chinn 
          SB 1388 Analysis
          Hearing Date:  May 9, 2000