BILL ANALYSIS 1 SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE DEBRA BOWEN, CHAIRWOMAN SB 1388 - Peace Hearing Date: May 9, 2000 S As Amended: May 4, 2000 FISCAL B 1 3 8 8 DESCRIPTION Current law provides the California Energy Commission (CEC) with responsibility for licensing large power plants. Certain state and local agencies have advisory responsibilities to the CEC under particular circumstances. This bill requires those state and local agencies to provide recommendations within 180 days of the filing of an application to license a power plant. Current law requires the CEC to prepare a geothermal resource sufficiency study whenever it considers a proposal to site a geothermal electric generation facility. This bill deletes that requirement. Current law provides the Federal Energy Regulatory Commission (FERC) with authority to set electric transmission rates. This bill requires the CPUC, in conjunction with the Electricity Oversight Board (EOB), to facilitate FERC approval of reasonable transmission facility planning and engineering expenditures, even if those expenditures do not result in operational transmission facilities. This bill further requires the CPUC to approve all reasonable transmission planning, design, and engineering expenditures irrespective of whether those expenditures result in an operational transmission line. Current law provides for competition in the generation and sale of electricity. This bill requires the California Public Utilities Commission (CPUC) to conduct specified pilot projects to gauge small consumer responsiveness to energy usage and price information. BACKGROUND This bill has three distinct parts: Part 1 deals with power plant licensing improvements recommended by the CEC, Part 2 deals with recovering transmission planning costs from customers, and Part 3 establishes pilot programs to test small customer responsiveness to energy price and usage information. Part 1 - CEC Report Recommendations In March 2000, the CEC issued a report recommending a number of improvements to its power plant siting process. That report, which was reviewed by this Committee during an April 11, 2000, informational hearing, suggests a number of statutory, regulatory, and management changes. This bill implements two of the CEC's recommended statutory changes, the first of which deletes the requirement that the CEC perform a steam-field adequacy analysis for geothermal projects. Geothermal projects are electrical generation projects which utilize underground heat and steam as the energy source (e.g. the Geysers power plants). A steam-field adequacy analysis investigates whether there is enough underground heat and steam to power the plant through its projected life. The CEC recommended deleting this requirement because in a competitive generation market, it believes the responsibility of ensuring an adequate fuel supply, in this case heat and water, should fall to the power plant developer and not rest with the CEC. The second of the recommended changes implemented by this bill is a requirement that state and local governmental entities having jurisdiction or an interest in a proposed power plant make their recommendations within 180 days of the filing of the project. The CEC noted that it has a statutory one year requirement to process power plant siting applications and its ability to meet that deadline is jeopardized in cases where state and local agencies provide their comments late in the process. While the CEC has entered into Memoranda of Understanding (MOU) with the California Air Resources Board, the Department of Toxic Substance Control, the California Independent System Operator, and a number of other agencies to establish a 180 day target for input, this bill applies a statutory requirement of 180 days to those agencies and to other entities not covered by such MOUs. Part 2 - Transmission Lines Transmission lines are an essential electric infrastructure and those lines owned by investor-owned electric utilities (IOU), such as PG&E and Southern California Edison, are rate regulated. The IOUs plan and engineer new transmission lines to serve their service territories, but they can't build those lines without approval from the Independent System Operator (ISO), the statutorily-created entity controlling the transmission system. The ISO evaluates all transmission facility proposals and considers alternate ways of meeting customer demand, such as building new power plants or alternative transmission facilities, then selects the least costly option. IOUs are concerned that if their transmission facilities aren't permitted to be built, they aren't assured that their planning and engineering costs for transmission facilities will be recoverable from customers. The failure to be able to recover those costs could discourage utilities from doing necessary planning, thereby impairing the future ability of the transmission system to operate reliably and efficiently. This bill proposes to resolve that concern by stating that the Legislature finds that reasonable expenditures for planning and engineering of transmission facilities is in the public interest and requires the CPUC and the EOB to jointly facilitate approval of those costs in the transmission rates approved by FERC. The bill further requires the CPUC to allow recovery of all reasonable expenditures for transmission planning, design, and engineering, regardless of whether such facilities become operational. Part 3 - Residential and Small Commercial Customer Pilot Projects Much of the effort in restructuring the electric industry was focused on creating a competitive market for electric generation - in other words, increasing the supply of electricity - but little work was done on addressing the issue of consumer demand, largely because the price for electricity was frozen. As electric rates are unfrozen, which is the case in the San Diego Gas & Electric Company (SDG&E) territory, customers will see variations in their electric bill based not just on changes in usage but also on changes in the price of electricity. While rates were frozen, consumers had little incentive to pay attention to when they were using electricity because the price for electricity was always the same. As rates become unfrozen, consumers who want to keep their bills low have an incentive to use their electricity at the least expensive times of the day - if they can easily figure out the price of electricity at a given time of day and if they are charged a price which varies by time of day. The author believes this consumer reaction, known as "demand responsiveness," is an important component of electric system reliability and of a well-functioning market. Encouraging demand responsiveness is particularly critical at a time when California is facing a squeeze in resources and the prospect of high energy prices under adverse climatic conditions. This bill establishes three pilot projects limited to residential and small commercial customers to test varying ways of providing consumers with that type of pricing information. The first provides real-time (minute-to-minute) usage information ; the second provides for peak, mid-peak, and off-peak usage and rate information coupled with a utility rate schedule that differentially prices electricity at peak, mid-peak and off-peak rates, while the third provides for hourly usage and rate information coupled with a utility rate schedule that allows prices to vary by the hour. The author believes obtaining a better understanding of the extent to which various levels and types of usage and price information will trigger demand responsiveness is essential in understanding the cost effectiveness of the types of investments and opportunities that should be afforded customers. The bill requires all utilities that no longer have frozen rates to participate in the three pilots, which means only SDG&E will be immediately affected by the bill. However, once Pacific Gas & Electric Company (PG&E) and Southern California Edison (SCE) are out from the rate freeze (which should happen sometime in 2001), then some of their customers will also have to participate in the three pilot programs. The total pilot program participation is limited to 3% of the residential and small commercial customers of each utility and is further limited to the minimum number of customers needed to develop a statistically valid sample for the two pilots with time-of-use rates. The design and implementation of the pilot study shall include interested energy service providers and equipment manufacturers. Each of the three pilot programs is required to use a standard usage information output interface, which the bills defines, and the CPUC will select the interface that conforms with nationally recognized standards. This bill requires that the interface be secure, safe, and the most cost-effective available. The purpose of a standard usage information output interface is to establish an industry standard, which in turn will drive the creation of compatible devices which use that consumer information The cost of the pilot programs is recoverable from customers. KEY QUESTIONS 1.Does requiring state and local agencies to comment on power plant siting proposals within 180 days provide them with adequate time to prepare comments? 2.Should the CPUC and the EOB be required to facilitate approval of utility transmission planning costs in the overall transmission rates approved by FERC? 3.Are the pilot programs created by this bill adequate and necessary for determining consumer demand responsiveness? COMMENTS 1) Timeline For Input . As noted in Part 1 of the "Background" section, the CEC is required to process power plant siting applications within a year of receiving a completed application and its ability to meet that deadline is jeopardized in cases where state and local agencies provide their comments late in the process. To alleviate that problem, this bill requires state and local governmental entities having jurisdiction or an interest in a proposed power plant to make their recommendations within 180 days of the filing of the project. 2) Transmission Planning Cost Recovery . As noted in Part 2 of the "Background" section, this bill requires the CPUC and the EOB to facilitate FERC approval of reasonable transmission facility planning and engineering expenses - even if those expenditures don't result in operational transmission facilities. The author believes electrical corporations shouldn't be discouraged from engaging in transmission planning because of concerns that the costs of such planning may not be recovered in the event that the project isn't ultimately needed. FERC's practice is to allow recovery of only 50% of such costs. By directing the CPUC and EOB to essentially go to bat for the utilities at FERC, the author hopes to clearly express California's policy preferences to FERC and to persuade the agency to allow for more than 50% cost recovery. To more clearly accomplish this goal, the author and committee may wish to make two clarifications : The first sentence of paragraph (b) of this section (Page 17, Line 13) seems to inadvertently require the CPUC to allow for cost recovery of all transmission planning expenditures even if they're denied by the FERC. This doesn't seem to be the intent of the overall provision and the author and committee may wish to consider clarifying this line. Second, while the first paragraph of this provision (Page 17, Line 3) allows "reasonable" expenditures to be deemed prudent and be recoverable, that same terminology isn't carried over to the second paragraph. The term "reasonable" is important because it implies a CPUC review and allows for obviously inappropriate expenditures to be excluded. The author and committee may wish to consider inserting the term "reasonable" on Page 17, Line 23. 3) Timing of Pilot Projects . The bill requires all investor owned utilities to establish these pilot programs within 15 months of the date at which their customers are out of the rate freeze. For SDG&E, that means it will be required to set up such a program within 15 months of the enactment of this bill, which will be January 1, 2001. However, since PG&E and SCE may not end their rate freeze until late 2001, it could be two years between the time when the SDG&E pilot projects begin and the PG&E and SCE projects get off the ground. The bill requires all of the pilot projects to have identical offerings so the results of the pilots can be easily compared. However, given the potentially long time interval between pilots, there may be changes in technology or practice - or useful results from the first pilots - that the author may wish to incorporate into the second set of pilot projects. As such, the author and committee may wish to consider giving the CPUC the authority to adjust or waive the additional pilot programs if it doesn't feel their implementation is warranted. 4) Size of Pilot Projects . The pilot project in each area is limited to 3% of the residential and small commercial customers of each utility, and two of the three programs within each project are capped at the minimum number of customers needed to develop a statistically valid sample. The author and committee may wish to consider clarifying that the 3% figure applies to the total aggregate number of customers taking part in all three pilot programs. 5) Cost of Pilot Projects . Under this bill, the utilities would select the residential and small customers to take part in the pilot project and the cost of the project would be recovered in the rates spread across the entire rate base, including both small and large customers. According to information provided by the author's office, the standard usage information output interface required by the bill costs about $35 per customer, though that doesn't include the cost of the visual display device in the home or the connection from that display device to the output interface. If the total equipment cost is, for example, $70 per home and SDG&E includes 3% of its total residential and small customer base in the program, the total cost of the pilot in the SDG&E territory could approach $2.5 million, though other estimates (based on a $200 equipment cost) have been as high as $7 million.. If the total cost of the project is of concern, the author and committee may wish to consider limiting participation in each of the three programs to no more than the minimum number of people necessary to provide a statistically valid sample. Currently in the bill, this limitation is imposed on the second and third pilot projects, but not on the first (Page 13, Lines 33-36). 6) Display Error . Providing customers with easily accessed information is a cornerstone to a sound test of demand responsiveness, but two of the pilot projects inadvertently exclude a visual display capability. The author and committee may wish to consider correcting this drafting error by deleting the prohibition of the visual display module in two of the pilot projects and instead requiring them to have a visual display module (Page 12, Line 30 and Page 12, Line 40). 7) Rate Schedules . Under the electric restructuring statutes, electric utilities simply pass through their cost of acquiring electricity. This bill contemplates the utility establishing "rate schedules" which aren't necessarily limited to cost pass-throughs and which may require some averaging by the utility. The author and committee may wish to consider clarifying that the utility rate schedules adopted pursuant to this bill are subject to CPUC approval and should reflect the utility's actual energy costs for the relevant time intervals. This could be accomplished by making the following changes: Page 12, Line 26, before "Electrical corporations" add "Subject to commission approval,"; Page 12, Line 28, after "use" add "that reflects the electrical corporation's actual energy cost"; Page 12, Line 34, before "Electrical corporations" add "Subject to commission approval,"; Page 12, Line 36, delete "net"; and Page 12, Line 37, end the sentence after "cost" and delete the remainder of the sentence. 8) Customer Participation . Two of the pilot projects created by this bill involve changing rate schedules. Residential and small-commercial customers typically have rates which don't vary by time or season. Under two of the pilot projects, the customers will have rates which vary by time of day and time of year, and they'll have timely information as to how those rates are changing. This is a significant change for customers which may or may not be welcome by all. The author and committee may wish to consider how customers are selected for the pilot projects. Should the utility be able to select the customers or should customers be able to volunteer to participate? In the event the utility selects the customers, should those customers be able to "opt out' of participating? 9) Interpreting The Results of The Pilot Projects . The pilot studies are intended to answer basic questions about small customer demand responsiveness, including whether any behavioral changes justify wide scale implementation of these programs. In a competitive electric market, this data may have value to other potential providers of services and it would seem to be in keeping with the spirit of the bill to make this information widely available. While the bill requires a report to the Legislature on the study results , the author and committee may wish to consider making the study data publicly available, subject to sufficient confidentiality of individual customer information. 10) Technically Speaking . The author may wish to consider the following technical amendments to the measure: a) Page 5, Line 32: After "is" insert "not" b) Page 5, Line 34: Replace "is" with "may be" c) Page 6, Line 31: Before "Expenditures" insert "Reasonable" d) Page 6, Line 34: After "interest" delete ", reasonable and" and insert "and are deemed" e) Page 11, Line 40: Replace "(c)" with "(a)" f) Page 12, Line 20: After "customer" insert ", electrical corporation," g) Page 14 Line 18: Replace "(c)" with "(a)" POSITIONS Sponsor: Author Support: Sempra Energy Oppose: California Manufacturers & Technology Association Randy Chinn SB 1388 Analysis Hearing Date: May 9, 2000