BILL ANALYSIS
AB 995
Page 1
Date of Hearing: May 12, 1999
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Carole Migden, Chairwoman
AB 995 (Wright) - As Amended: April 14, 1999
Policy Committee: Utilities and
Commerce Vote: 11-0
Urgency: No State Mandated Local
Program:NoReimbursable:
SUMMARY :
This bill requires the Independent System Operator (ISO) to
coordinate the implementation of legislative policy, making an
efficient and reliable transmission grid a key consideration
with regard to planning, siting, and permitting processes and
enhancements and additions to the grid.
FISCAL EFFECT :
No fiscal impact.
COMMENTS :
Purpose . Presently, both transmission owners and ISO have roles
in the planning of a reliable transmission grid, but the roles
and responsibilities are unclear and need to be more clearly
defined. The author indicates that he has been in discussion
with numerous affected parties including the transmission
owners, ISO, Electricity Oversight Board, and municipal
utilities. This bill is intended as an opportunity to develop
clear policies for transmission planning to ensure a reliable
transmission grid for electricity customers.
Analysis Prepared by : Chuck Nicol / APPR. / (916)319-2081