BILL ANALYSIS                                                                                                                                                                                                    






                       SENATE JUDICIARY COMMITTEE              S   
                      Charles M. Calderon, Chairman            B
                         1995-96 Regular Session
                                                               1
                                                               2
                                                               8
                                                               6
                                                        
SB 1286 (Mountjoy)
As Amended on April 26, 1995
Hearing date:  May 2, 1995
Civil Code
GEH:ilc



                        CONSTRUCTION CONTRACTS
                       LIMITATIONS ON LIABILITY
          PENALTIES FOR LATE PAYMENTS TO DESIGN PROFESSIONALS



                               HISTORY



Source:  Consulting Engineers and Land Surveyors of California
         American Institute of Architects, California Chapter

Related Pending Legislation:  None known



                              KEY ISSUES

1.   SHOULD PROVISIONS IN CONSTRUCTION CONTRACTS LIMITING THE  
     LIABILITY OF ONE PARTY TO ANOTHER BE VALID, NOTWITHSTANDING THE  
     DOCTRINE OF UNCONSCIONABILITY AND NOTWITHSTANDING ANY OTHER  
     PROVISION OF STATUTORY OR COMMON LAW?

2.   SHOULD OWNERS OF PUBLIC OR PRIVATE WORKS PROJECTS BE REQUIRED  TO  
    PAY DESIGN PROFESSIONALS A STATUTORY LATE FEE IF THEY DO NOT  PAY  
    WITHIN SPECIFIED PERIODS OF TIME?


                                                        (more)










    A.       SHOULD DESIGN PROFESSIONAL BE ACCORDED THE SAME  
        PROTECTION
             AS CONTRACTORS AND SUBCONTRACTORS?

    B.       SHOULD THE EXEMPTION FOR OWNER-OCCUPIED SINGLE-FAMILY  
        HOMES  APPLY TO HOMES COSTING MORE THAN $100,000 TO BUILD?






































                                                        (more)







SB 1286 (Mountjoy)
Page 3

                               PURPOSE

This bill has two purposes:

1)  To limit the legal effect of a state appeals court case which  
    held that a contractual provision limiting the liability of an  
    engineering firm to a design professional was unenforceable; and

2)  To ensure prompt payment of design professionals by owners of  
    construction projects by providing for statutory late fees to be  
    paid by owners paying design professionals after specified  
    periods of time.

 Liability Limitations in Construction Contracts

 Existing law, Section 2782 of the Civil Code, declares void any  
provision in a construction contract which indemnifies one party  
against claims for damages by third parties arising from the party's  
negligent or willful misconduct.

However, Section 2782.5 clarifies that Section 2782 does not make  
prohibit the parties to a construction contract from negotiating and  
expressly agreeing to a provision which limits the liability of one  
of the parties to the other party.

In  Markborough California, Inc. v. Superior Court (1991) 227  
Cal.App.3d 705, the court held that Section 2782.5 does not impose  
upon parties an affirmative duty to specifically advise the other  
party of the inclusion of a liability limitation clause in the  
contract or to inform the other party of the risks involved in the  
project.

In  Viner v. Brockway (1994) 30 Cal.App.4th 1307, as modified by 31  
Cal.App.4th 746i, the court held that liability limitation  
provisions in construction contracts were subject to the common  law  
principles of unconscionability and public policy, as those have  
been applied to contracts limiting liability since the state Supreme  
Court's decision of  Tunkl v. Regents of University of  California  
(1963) 60 Cal.2d 92.

Applying those principles, the  Viner court refused to enforce a  
liability limitation provision in a contract between an engineering  


                                                        (more)







SB 1286 (Mountjoy)
Page 4

firm and a homeowner, even though the homeowner was represented by  
counsel, principally because neither the homeowner nor his counsel  
was trained to understand the technical engineering issues which  
were the subject of the contract.

Last month, the state Supreme Court ordered the  Viner case  
de-published, meaning the case no longer has precedentual value.

 This bill amends Section 2782.5 by providing that parties to a  
construction contract may negotiate for, and expressly agree to, 


































                                                        (more)







SB 1286 (Mountjoy)
Page 5

a liability limitation " notwithstanding any other provision of  
 statutory or common law, including the doctrine of  
 unconscionability...."

The bill also contains a legislative declaration that these changes  
to Section 2782.5 are intended to limit the legal effect of  Viner  v.  
Brockway, so that that decision does not apply to contracts entered  
into on and after January 1, 1996.

 Prompt Pay Provisions

 Existing law, Civil Code Section 3260.1, establishes a special  
penalty for the late payment of licensed contractor in a private  
work of improvement contract.  A 2 percent per month penalty is  
imposed in lieu of interest if a progress or retention payment is  
not timely made.  Attorneys' fees are awarded to a prevailing party  
in an action to collect wrongfully withheld funds.  This section  
allows parties to agree in writing to a contrary arrangement.

Existing law also provide special prompt payment protections for  
licensed contractors in public works contracts.  A state or local  
agency is liable to a licensed contractor for a penalty of 10  
percent per year on the unpaid amount if a progress payment is not  
paid within 30 days of demand (Sections 10261.5 and 20104.50 of the  
Public Contracts Code), and is liable for a penalty of 2 percent per  
month in lieu of interest if the retention payment is not paid  
within 60 days after the date of completion.

Existing law does not establish any special penalty for the late  
payment of a design professional (licensed architect, professional  
engineer or land surveyor).  However, in any contract with a "small  
business" for services or property, a state agency is liable to the  
business for a penalty of 1/4 percent per day of the amount of the  
undisputed claim due, if a proper claim is not paid within 30 days  
without reasonable cause. (Section 926.15 of the Government Code)   
For parties other than "small businesses", a state agency is liable  
for an interest penalty fee if a proper claim is not paid within 50  
calendar days of the date of invoice.  (Section 926.17 of the  
Government Code).  The penalty is established at a rate of 1 percent  
above the rate accrued by the state's Pooled Money Investment  
Account.



                                                        (more)







SB 1286 (Mountjoy)
Page 6

 This bill would enact "prompt-pay" protections for design  
professionals, in contracts for local public or private works of  
improvement entered into on or after January 1, 1996, as follows:

1)  A local public agency or private owner would be required to pay  
    any "prime design professional" (a design professional with a  
    contract directly with the owner) within 30 days of receiving a  
    written demand in accordance with contract for a progress  
    payment, and within 45 days of receiving a written demand for a  
    final retention payment.


































                                                        (more)







SB 1286 (Mountjoy)
Page 7


2)  If an owner fails to make timely payment as provided in the  
    bill, the owner would be liable for a statutory penalty 1 and  
    1/2 percent per month on the wrongly withheld amount, in lieu of  
    any interest due, up to a maximum amount of 12 percent of the  
    total amount due.

3)  If there is a good faith dispute over the amounts owned, the  
    owner may withhold from the payment an amount not to exceed 150  
    percent of the disputed amount.  Any amount withheld pursuant to  
    this provision would not be subject to the late penalty.

4)  A prevailing party would receive its reasonable attorneys' fees  
    and costs in any action to collect improperly withheld funds.  
5)  The monetary penalty, and any attorneys' fees and costs awarded  
    in an enforcement action, would be separate from any rights the  
    design professional has to file a mechanics or design  
    professionals lien or to serve a stop notice.
    
6)  A "prime design professional" would be required to pay a  
    subconsultant design professional within 15 days of receiving a  
    progress payment or a final retention payment.  Late payments by  
    a prime design professional to s subcontractor design  
    professional would be subject to the same provisions as late  
    payments by an owner to a prime design professional.


The bill allows parties to agree in writing to a contrary  
arrangement.

The bill would not apply to any contract relating to a  
single-family, owner-occupied residence where the construction costs  
are less than $100,000.  The bill would also not apply to state  
agency contracts which are governed by Sections 926.15 or 926.17 of  
the Government Code, which are described above.



                               COMMENT

1.   Liability limitation provisions in construction contracts



                                                        (more)







SB 1286 (Mountjoy)
Page 8

    a)      The  Viner case 

            The Consulting Engineers and Land Surveyors of  
        California (CELSOC) have requested this bill's amendments to  
        Section 2782.5 because of the concern of its members over  
         Viner v.  Brockway,  supra.

            CELSOC argues that if a liability limitation provision  
        in an engineering contract is unconscionable merely because  
        the client is not trained in engineering, then they will 


































                                                        (more)







SB 1286 (Mountjoy)
Page 9

    almost never be able to contractually limit their liability for  
    design errors to the amount of the contract price, as is the  
    common practice.  Even though  Viner has been de-published by the  
    state  Supreme Court, CELSOC believes this bill is necessary to  
    ensure "that there be no more  Viner cases.

             Viner does appear to be a poorly reasoned decision; it  
        is highly unusual to declare a contract unconscionable when  
        the party seeking to avoid the contract was represented by  
        counsel, especially when the other party was not.

            Nevertheless, the decision has some merit.  The court  
        was concerned about the fact that the homeowners in the case  
        were contracting for services which they were being required  
        to perform by the city because their home was sliding down  
        the hillside.  The court seems to have believed this  
        compulsion by the city, and the need to save their home, put  
        the homeowners in the type of "take it or leave it" position  
        usually associated with unconscionable liability waiver  
        contracts.

            Therefore, if were good precedent,  Viner it would stand  
        for something more complex than the proposition that the  
        contracts were void because the homeowners and their lawyers  
        did not understand engineering principles.

    b)       The proposed amendment to Section 2782.5

            The sponsors' proposal for legislatively responding to  
         Viner is rather extreme.

            As drafted, the amendment to Section 2782.5 would  
        validate any liability waiver provision in a construction  
        contract, no matter how unfair, no matter how disparate the  
        bargaining the power.  The term "notwithstanding any other  
        provision of statutory or common law" would even appear to  
        validate liability limitation provisions procured through  
        fraud or duress.
            
            The sponsors recognize that the language is overbroad,  
        and they have indicated a willingness to focus the amendment  
        to Section 2782.5 to the issue raised by  Viner:  claims of  


                                                        (more)







SB 1286 (Mountjoy)
Page 10

        unconscionability based upon differences in the professional  
        licensure or education of the parties or the parties'  
        representatives.

            Even this more limited approach is problematic, however.  
         Differences in the educational levels of parties has always  
        been an element in determining unequal bargaining power,  
        which is one of the central aspects of the unconscionability  
        doctrine.



































                                                        (more)







SB 1286 (Mountjoy)
Page 11


            Declaring contracts, such as ones with liability  
        limitation provisions, unconscionable or void as a matter of  
        public policy is one of the classic examples of an activity  
        which is best left to the courts.  It is peculiarly within  
        the competence of the judiciary to evaluate all of the  
        nuances of a particular fact pattern, and compare those  
        nuances to previous cases.

            This sponsor's desire to permanently excise the memories  
        of a single poorly reasoned case which is not even good  
        precedent does not seem sufficient justification to usurp  
        this traditional role of the judiciary by formulating  
        legislative standards of unconscionability.

             IS NOT THE DOCTRINE OF UNCONSCIONABILITY BEST LEFT TO  
        THE  DISCRETION OF THE COURTS?

2.   Prompt pay provisions

    a)       SHOULD DESIGN PROFESSIONALS BE GIVEN THE SAME PROTECTION  
        AS  CONTRACTORS?

            The sponsors argue that design professionals are just as  
        important a part of the construction process as are  
        contractors and subcontractors, and that they therefore  
        should be accorded the same protection against late payment  
        by project owners.

            According to the American Institute of Architects:

            "In this tough fiscal climate, we are seeing an alarming  
        trend on the part of public owners who are taking advantage  
        of design professionals by unreasonably delaying payment for  
        services properly rendered.  Architects are being put in an  
        economic straight jacket where firms are virtually financing  
        owners' projects while awaiting overdue payments."

            The other sponsor, CELSOC, emphasizes that, by allowing  
        parties to contract for different provisions for payment of  
        late penalties, the bill adequately protects the rights of  
        individuals contracting with designers.


                                                        (more)







SB 1286 (Mountjoy)
Page 12


            It appears that the only opposition to this prompt pay  
        provision is from the California Municipal Utilities  
        Association, which is concerned that 30 days may not be  
        enough time to verify satisfactory completion of work, and  
        cites logistical problems like scheduling meetings and  
        conducting site visits.

            The Association of California Water Agencies (ACWA)  
        appears to have begrudgingly withdrawn its opposition to the  
        measure:

































                                                        (more)







SB 1286 (Mountjoy)
Page 13


            "We do not believe there is a problem to be solved here.  
         In most, if not all cases, specific payment requirements  
        are spelled out in contracts....  While we do not believe  
        there is a need for the measure, we would be able to  
        withdraw our opposition if it were amended to provide that  
        its provisions apply only if specific payment provisions are  
        not included in a contract."

            In response to ACWA's concern, the bill has been amended  
        to allow parties to agree to contrary provisions in writing.  
         These amendments, however, are ambiguous, and should be  
        re-drafted to clarify the author's intent that the statute  
        applies unless the parties agree in writing to contrary late  
         penalty provisions.

            SHOULD NOT THIS TECHNICAL AMENDMENT BE ADOPTED?

    b)       Exemption for owner-occupied residences

            This bill's statutory late payment fee could not be  
        assessed against owners who have contracted with a design  
        professional for an owner-occupied single-family residence  
        where the construction costs are less than $ 100,000.

            This $100,000 figure seems so low that it might render  
        this a meaningless provision.  Most people who hire an  
        architect to design a custom home do so for homes that cost  
        more than $100,000.  The committee may wish to solicit  
        testimony on what a more appropriate amount would be.

    SHOULD THE 100,000 FIGURE BE SIGNIFICANTLY INCREASED?


Support:      Consulting Engineers and Land Surveyors of California
              American Institute of Architects, California Chapter.


Opposition:   California Municipal Utilities Association; Consumer  
              Attorneys of California; Calfornia Bankers Association;  
              Association of California Water Agencies.











SB 1286 (Mountjoy)
Page 14


Prior Legislation:  AB 295 (1993) Vetoed (prompt pay provisions)

                                *******