BILL ANALYSIS                                                                                                                                                                                                    



                                                                  SB 1059 
                                                                  Page  1

          Date of Hearing:   August 16, 2006

                        ASSEMBLY COMMITTEE ON APPROPRIATIONS
                                   Judy Chu, Chair

                   SB 1059 (Escutia) - As Amended:  August 7, 2006 

          Policy Committee:                               
          UtilitiesVote:11-0
                        Local Government                        7-0

          Urgency:     No                   State Mandated Local Program:  
          Yes    Reimbursable:              Yes

           SUMMARY  

          This bill authorizes the California Energy Commission (CEC),  
          according to a specified process, to designate electric  
          transmission corridors zones (TCZs) for future construction of  
          high-voltage (at least 200 kilovolt) transmission lines  
          consistent with the states' needs and objectives. This bill  
          also:

          1)Specifies the commission may designate a TCZ on its own motion  
            or in response to an application from a person seeking a TCZ  
            designation based on its future plans to construct a  
            high-voltage electric transmission line. 

          2)Requires the commission to charge an applicant for all costs  
            associated with reviewing the application. For a designation  
            proposed by the commission, the commission's costs are to be  
            covered by revenues from the existing energy resources  
            surcharge (for which the commission is funded through the  
            Energy Resources Programs Account).

          3)Makes the CEC the lead agency, for purposes of the California  
            Environmental Quality Act (CEQA), for the designation of any  
            TCZ.

          4)Requires the CEC to notify affected cities, counties, state  
            and federal agencies, and Native American tribal governments  
            of a proposed TCZ designation and requests that these entities  
            review and provide comments regarding the application.

          5)Authorizes a city or county, upon receiving a request per (4),  








                                                                  SB 1059 
                                                                  Page  2

            to request a fee from the commission to cover the city's or  
            county's costs to review a proposed designation.

          6)Requires an affected city or county, upon CEC designation of a  
            TCZ, to consider the designation when making a land use change  
            within or adjacent to the TCZ.

          7)Requires a affected city or county, within 10 days of  
            accepting as complete an application for a development project  
            that could threaten the potential construction of a  
            high-voltage line within a TCZ, to notify the CEC of the  
            proposed project.

          8)Authorizes the CEC, upon notification per (7), to recommend  
            revisions to the project to eliminate the threat, and requires  
            the city or county to consider the CEC's recommendation and  
            provide written comments.



           FISCAL EFFECT  

          1)The CEC indicates a need for eight positions at a cost of  
            about $900,000 annually for technical and planning staff to  
            develop the TCZ designations, including CEQA work and outreach  
            to local entities. [Energy Resources Programs Account]

          2)The state will incur additional costs to the extent cities and  
            counties seek reimbursement for their costs to review  
            applications for TCZs designated by the CEC. These costs,  
            which would depend on the number of TCZs and the number of  
            jurisdictions involved are unknown.

           COMMENTS  

           1)Purpose  . According to the author, the purpose of this bill,  
            which is sponsored by the Governor's Office, is to provide  
            direction on electric transmission infrastructure and to  
            coordinate planning and permitting for transmission projects,  
            which is currently divided between a multitude of federal,  
            state, and local agencies, as well as private corporations,  
            who either own or manage pieces of the transmission grid.

           2)Background  . The CEC's 2003 Integrated Energy Policy Report  
            claims that the state's bulk transmission system needs major  








                                                                  SB 1059 
                                                                  Page  3

            upgrades and improvements.  The CEC says there is a gap  
            between its policy documents and the construction of  
            high-voltage transmission lines.  The commission claims no one  
            is identifying the corridors needed for future transmission  
            lines, nor is anyone protecting these pathways from  
            encroachment by development.  

            In response to the fact that no specific state agency was  
            charged with planning for the future of the transmission  
            system as a whole, SB 1565 (Bowen)/Chapter 962 of 2004, was  
            enacted to require the CEC to develop a strategic transmission  
            plan that recommends actions required to implement investments  
            needed to ensure reliability, relieve congestion, and to meet  
            future growth in load and generation. The strategic plan was  
            required to be included in the IEPR adopted on November 1,  
            2005. As part of the SB 1565 process, the CEC identified and  
            evaluated potential transmission corridors to accommodate  
            future siting and construction of needed transmission lines.  
            The CEC transmission plan is only a recommendation and does  
            not possess the authority to formally designate such corridors  
            to ensure that they will be available when needed.

           3)Opposition  . Just as a local zoning ordinance does not approve  
            specific developments, the designation of a TCZ pursuant to  
            this bill would not constitute approval in whole or in part of  
            any specific transmission project, nor would TCZ designation  
            substitute for any of the federal, state or local permits  
            required to construct a transmission line itself.  Similarly,  
            designation of a TCZ would not give eminent domain authority  
            to a project proponent, or justify condemnation of specific  
            properties necessary to accommodate the construction of a  
            transmission line.  Those procedures follow an application to  
            construct a transmission line with the relevant permitting  
            agencies, like the PUC and others, and not the CEC. 

            The PUC is opposed to this bill because currently the PUC is  
            the lead agency in the siting of all transmission lines and  
            substations for applications submitted by the investor-owned  
            utilities. The PUC is concerned that this bill would confuse  
            and complicate this arrangement by turning aspects of the  
            siting of transmission lines over to the CEC by allowing  
            applicants to apply directly to the CEC for transmission  
            corridor designation, and by requiring the CEC to be the lead  
            CEQA agency. This bill creates a new planning tool which  
            doesn't currently exist and doesn't conflict with any existing  








                                                                  SB 1059 
                                                                  Page  4

            authority.

             In response  , the author indicates that designation of  
            transmission corridors is intended as an optional up-front  
            planning process, to identify areas suitable for future  
            transmission lines, and that will precede the permitting  
            process for any particular line. The PUC would continue as the  
            permitting agency for the investor-owned utilities that are  
            subject to its jurisdiction.  Among its decision-making  
            responsibilities for IOU transmission applications, the PUC  
            will also remain the CEQA lead agency.

           Analysis Prepared by  :    Chuck Nicol / APPR. / (916) 319-2081