BILL ANALYSIS                                                                                                                                                                                                    



                                                                  SB 1059
                                                                  Page  1

          Date of Hearing:   June 26, 2006

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                               Lloyd E. Levine, Chair
                    SB 1059 (Escutia) - As Amended:  May 16, 2006

           SENATE VOTE  :   34-1
           
          SUBJECT  :   Electric transmission corridors.

           SUMMARY  :   Authorizes the California Energy Commission (CEC) to  
          designate electric transmission corridor zones (TCZ), according  
          to a specified process, in which high-voltage electric  
          transmission lines may be built in the future.  Specifically,  
           this bill  : 

          1)Defines a TCZ as the geographic area necessary to accommodate  
            the construction and operation of one or more high-voltage  
            electric transmission lines typically no more than 1,500 feet  
            in width, with specified exceptions. 

          2)Permits the CEC to designate a TCZ on its own motion or by  
            application of a person, if the TCZ is consistent with the  
            needs and objectives set forth in the CEC's strategic plan  
            adopted for the state's transmission grid and included in the  
            Integrated Energy Policy Report (IEPR).

          3)Designates the CEC as the lead agency for all TCZs under the  
            California Environmental Quality Act (CEQA).

          4)Requires the CEC to confer with and coordinate with other  
            jurisdictions to identify long-term transmission needs of the  
            state.

          5)Identifies actions and timelines which the CEC must abide by  
            regarding designating a TCZ, including holding public  
            hearings, receiving comments, soliciting information, and  
            conducting commission prehearing conferences and hearings.

          6)Requires the CEC to regularly review and revise its TCZs as  
            necessary, and not less frequently than once every 10 years. 

          7)Requires each city or county to consider the designated  
            corridor when making a determination regarding a land-use  
            change within or adjacent to a TCZ that could affect the  








                                                                  SB 1059
                                                                  Page  2

            viability to accommodate a transmission line planned within  
            the corridor.

           EXISTING LAW  :

          1)Requires the California Public Utilities Commission (PUC) to  
            certify the public convenience and necessity of a transmission  
            line before an investor-owned utility (IOU) may begin  
            construction (Certificate of Public Convenience and Necessity,  
            or CPCN).  The CPCN process includes environmental review of  
            the proposed project under CEQA.  The CPCN confers eminent  
            domain authority for construction of the project.

          2)Requires the CEC to assess electricity infrastructure trends  
            and issues facing California and develop and recommend energy  
            policies for the state to address and resolve such issues as  
            part of its biennial IEPR.

          3)Requires the CEC to adopt a strategic plan for the state's  
            electric transmission grid by November 1, 2005, which  
            recommends actions required to implement investments needed to  
            ensure reliability, relieve congestion, and meet future growth  
            in load and generation.

           FISCAL EFFECT  :   Unknown.

           COMMENTS  :   According to the author, the purpose of this bill is  
          to provide direction on electric transmission infrastructure and  
          to coordinate planning and permitting transmission projects  
          which is currently divided between a multitude of federal,  
          state, and local agencies, as well as private corporations, who  
          either own or manage pieces of the transmission grid.

          1)   Background  :  About 75% of the state's transmission grid is  
          owned by the IOUs.  The California Independent System Operator  
          (CAISO), a not-for-profit public benefit corporation, is charged  
          with operating the IOUs' transmission grid and managing the flow  
          of electricity.  (The CAISO also operates municipal utility's  
          transmission lines that have requested that service from CAISO.)  
          The CAISO plans for and recommends transmission projects within  
          its control area by soliciting information from the transmission  
          owners.  The CAISO works with a variety of stakeholders and  
          performs engineering and economic studies on proposed projects  
          to determine the potential benefits.   









                                                                  SB 1059
                                                                  Page  3

          The CAISO provides the transmission plans to the Electricity  
          Oversight Board (EOB) for review.  The EOB is statutorily  
          directed to provide oversight of the CAISO.  The EOB conducts  
          reviews and monitors CAISO operations, and the CAISO's wholesale  
          markets and transmission grid services.  The EOB participates on  
          behalf of California in western interstate regional market  
          monitoring and transmission structures and evaluates the CAISO  
          plan to ensure coordination.  Because the Federal Energy  
          Regulatory Commission (FERC) authorizes the CAISO tariffs, the  
          EOB initiates regulatory actions and interventions when  
          necessary at the FERC to protect California consumers at  
          proceedings regarding electricity transmission, including cases  
          that set rates for use of the transmission grid.  Due to the  
          EOB's participation in the western interstate regional  
          transmission structures and its oversight of the CAISO wholesale  
          transmission grid,  the committee may wish to add the EOB to the  
          list of entities from which the CEC would request comments on  
          the suitability of the proposed TCZ. 
           
          The responsibility for actually building the transmission lines  
          lies with the transmission-owning utilities.  Most of these  
          utilities need to obtain approval from the PUC before they can  
          construct new transmission lines.  The PUC conducts a public  
          hearing process and issues a CPCN if it deems the project is  
          warranted.  The utilities must then initiate a filing at the  
          FERC to request cost-recovery for both inter- and intra-state  
          transmission lines.

          A significant share of the state's transmission grid is owned by  
          municipal utilities and outside the jurisdiction of the ISO or  
          the PUC.  Similar to IOUs, municipal utilities possess eminent  
          domain authority to acquire rights-of-way for transmission  
          lines.  

          2)   An integrated policy:   The CEC's 2003 IEPR claims that the  
          state's bulk transmission system needs major upgrades and  
          improvements.  The CEC says there's a gap between its policy  
          documents and the utilities' construction of high-voltage  
          transmission lines.  The CEC claims that no one is identifying  
          the corridors needed for future transmission lines, nor is  
          anyone protecting these pathways from encroachment by  
          development.  

          In response to the fact that no specific state agency was  
          charged with planning for the future of the transmission system  








                                                                  SB 1059
                                                                  Page  4

          as a whole, SB 1565 (Bowen) (Chapter 962, Statutes of 2004) was  
          enacted to require the CEC to develop a strategic transmission  
          plan that recommends actions required to implement investments  
          needed to ensure reliability, relieve congestion, and to meet  
          future growth in load and generation.  The strategic plan was  
          required to be included in the IEPR adopted on November 1, 2005.  
           As part of the SB 1565 process, the CEC identified and  
          evaluated potential transmission corridors to accommodate future  
          siting and construction of needed transmission lines.  The CEC  
          transmission plan is only a recommendation and does not possess  
          the authority to formally designate such corridors to ensure  
          that they will be available when needed.  The CEC plan  
          recommended legislation to give it authority to formally  
          designate TCZs, which led to this bill.

          3)   The federal TCZ planning process  :  The federal Energy Policy  
          Act of 2005 directs the Secretaries of federal departments,  
          including Energy, the Interior, and the Bureau of Land  
          Management to review, designate, and adopt major energy  
          corridors across 11 states.  The goal is to avoid time-consuming  
          project-by-project reviews. Federal energy regulators also were  
          given authority to designate power lines in the national  
          interest, which would allow them to overrule federal agencies or  
          states or counties that withhold approval for segments of  
          projects.  

          The Energy Policy Act also provides the FERC with authority to  
          permit transmission projects which relieve transmission  
          congestion of national interest under certain conditions.  If  
          states with permitting authority take longer than one year to  
          act after the application is filed or the state imposes  
          conditions on a proposal such that it will not significantly  
          reduce transmission congestion or it is not economically  
          feasible, the FERC can pre-empt the state and authorize a  
          permit.  

          This bill would require the CEC to immediately notify affected  
          cities, counties, state and federal agencies, California Native  
          American Tribal governments in the jurisdiction of the TCZ.   
          Within 45 days of receipt of the application, the CEC must  
          commence public informational hearings. Within 155 days of the  
          final informational hearing, the CEC is required to conduct a  
          prehearing conference. Within 15 days of the prehearing  
          conference, the CEC is required to issue a hearing order and  
          conduct hearings. After the conclusion of hearings and no later  








                                                                  SB 1059
                                                                  Page  5

          than 180 days after certification of the environmental impact  
          report, the CEC is required to issue a proposed decision. 

          4)   Relationship to PUC process  :  Just as a local zoning  
          ordinance does not approve specific developments, the  
          designation of a TCZ pursuant to this bill would not constitute  
          approval in whole or in part of any specific transmission  
          project, nor would TCZ designation substitute for any of the  
          federal, state or local permits required to construct a  
          transmission line itself.  Similarly, designation of a TCZ would  
          not give eminent domain authority to a project proponent, or  
          justify condemnation of specific properties necessary to  
          accommodate the construction of a transmission line.  Those  
          procedures follow an application to construct a transmission  
          line with the relevant permitting agencies, like the PUC and  
          others, and not the CEC. 

          The PUC is opposed to this bill because currently the PUC is the  
          lead agency in the siting of all transmission lines and  
          substations for applications submitted by the IOUs.  The PUC is  
          concerned that this bill would confuse and complicate this  
          arrangement by turning aspects of the siting of transmission  
          lines over to the CEC by allowing applicants to apply directly  
          to the CEC for transmission corridor designation, and by  
          requiring the CEC to be the lead CEQA agency.  

          5)   NIMBY  :  The PUC is concerned that the bill's definition of  
          high-voltage transmission lines, defined as "at least 200  
          kilovolts or that is under the operational control of the  
          CAISO," is too broad and could affect more local jurisdictions  
          than may be necessary.  The PUC believes that a worthwhile  
          effort to designate TCZs should focus on the need for very  
          large-scale transmission, such as lines with an operating  
          capacity of at least 500 kilovolts.  Under this definition, all  
          large transmission lines, such as Sunrise, Devers-Palo Verde,  
          and the renewable resources transmission lines (Tehachapi, all  
          Phases) would qualify.  

          This bill would require the CEC to confer with cities and  
          counties, federal agencies and California Native American tribal  
          governments to identify appropriate areas within their  
          jurisdictions that may be suitable for a TCZ.  These entities  
          would likely propose to minimize the extent of TCZ designation  
          in their jurisdictions, which may have a policing effect that  
          could impose a level prudence when designating corridors.  As  








                                                                  SB 1059
                                                                  Page  6

          such, increasing the threshold may not be necessary; however,  
           the committee may wish to define high-voltage transmission as a  
          line that is not for the purposes of distribution  to ensure the  
          TCZs are only designated for high-voltage transmission.

          The original version of this bill provided the CEC with the  
          authority to pre-empt local land-use authority via the  
          designation of a TCZ.  It required the affected cities and  
          counties to integrate the TCZ designations into their general  
          plans and specific plans.  The author amended the bill to  
          require the each city or county to "consider the designated  
          corridor when making a determination regarding a land-use change  
          within or adjacent to the corridor that could affect its  
          continuing viability to accommodate a transmission line planned  
          within the corridor."   This amendment addressed the local  
          jurisdictions' concerns and they are no longer opposed.

          RELATED LEGISLATION:

          AB 974 (Nunez) requires the PUC to streamline the transmission  
          permitting process by eliminating regulatory overlap and  
          duplication, reducing review time, and expediting review of  
          projects with designated transmission corridors. This bill will  
          be heard in Senate Committee on Energy, Utilities &  
          Communications on June 27, 2006.


           REGISTERED SUPPORT / OPPOSITION  :

           Support 
           
          Governor's Office (sponsor)
          Sempra Energy
           
            Opposition 
           
          California Public Utilities Commission

           Analysis Prepared by  :    Gina Adams / U. & C. / (916) 319-2083