BILL ANALYSIS                                                                                                                                                                                                            1
        1





                 SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE
                             MARTHA M. ESCUTIA, CHAIRWOMAN
          

          SB 1059 -  Escutia/Morrow                              Hearing  
          Date:  April 5, 2005                 S
          As Amended:         April 4, 2005            FISCAL       B

                                                                        1
                                                                        0
                                                                        5
                                                                        9

                                       DESCRIPTION
           
           This bill  authorizes the California Energy Commission (CEC) to  
          designate electric "transmission corridor zones" (a feasible  
          corridor for future construction of high-voltage transmission  
          lines) and requires cities and counties to incorporate  
          CEC-designated zones into their land-use plans.

           Existing law:
           
             1)   Requires the California Public Utilities Commission (CPUC)  
               to certify the public convenience and necessity require a  
               transmission line before an investor-owned utility (IOU) may  
               begin construction (Certificate of Public Convenience and  
               Necessity, or CPCN).  The CPCN process includes environmental  
               review of the proposed project under the California  
               Environmental Quality Act (CEQA).  The CPCN confers eminent  
               domain authority for construction of the project.

             2)   Requires the CEC to assess electricity infrastructure  
               trends and issues facing California and develop and recommend  
               energy policies for the state to address and resolve such  
               issues as part of its biennial Integrated Energy Policy  
               Report (IEPR).
               SB 1389 (Bowen), Chapter 568, Statutes of 2002

             3)   Requires the CEC to adopt a strategic plan for the state's  
               electric transmission grid by November 1, 2005 which  
               recommends actions required to implement investments needed  
               to ensure reliability, relieve congestion and meet future  
               growth in load and generation.
               (SB 1565 (Bowen), Chapter 692, Statutes of 2004)
           
          This bill  :









           1)   Sets forth findings and declarations related to the need  
             for transmission investments and the importance of  
             designating corridors for future transmission lines.

           2)   Defines "transmission corridor zone" (TCZ) as the  
             geographic area necessary to accommodate the construction and  
             operation of one or more high-voltage electric transmission  
             lines (i.e. at least 200 kV), consistent with existing  
             adjacent land uses.

           3)   Authorizes the CEC to designate a TCZ on its own motion or  
             by application of a person who plans to construct a  
             high-voltage electric transmission line.

           4)   Requires a designated TCZ to be protective of the  
             environment to the extent feasible, be reflected in local  
             general and specific plans so as to integrate the electric  
             transmission needs of the state into local planning and be  
             wide enough to allow for alternative routes to be considered  
             where feasible.

           5)   Requires the CEC to be the lead agency for CEQA review of  
             all TCZs.

           6)   Requires the environmental impact report (EIR), or  
             environmental document prepared by the commission under a  
             certified regulatory program, to be used as a program EIR by  
             all cities and counties that amend their general or specific  
             plans to identify a designated TCZ.

           7)   Requires the CEC to review designated TCZs at least every  
             six years and, if the CEC finds a TCZ is no longer needed,  
             requires the CEC to rescind the designation.

           8)   Requires all subsequent state or local proceedings in  
             which a person seeks approval to build a transmission line  
             within a designated TCZ to use the CEC's EIR to the extent it  
             remains relevant to the project under review in the  
             determination of the reviewing agency.

           9)   Requires the CEC, in developing its strategic plan or  
             considering designation of a TCZ, to confer with cities and  
             counties, federal agencies and California Native American  
             tribes to identify suitable areas for a TCZ within their  









               jurisdictions.

             10)                                Requires the CEC, to the  
               extent feasible, to coordinate its identification of the  
               long-term transmission needs of the state with the land use  
               plans of cities and counties, federal agencies, and tribes.

             11)                                Prohibits the CEC from  
               designating a TCZ within the traditional land of a tribe  
               without consulting with the tribe.

             12)                                Requires the CEC to notify  
               and solicit comments regarding the designation of a TCZ from  
               affected agencies and conduct public hearings in affected  
               counties.

             13)                                Requires cities and counties  
               in which a designated TCZ is located to integrate the TCZ  
               into their general and specific plans during the next regular  
               plan revision, but not later than five years following  
               receipt of the CEC's decision.

             14)                                Requires CEC approval for  
               cities and counties to permit development within a designated  
               TCZ.

                                       BACKGROUND
           
          Like the state's highway and water systems, improvements to the  
          electric transmission system are critical to ease existing  
          congestion, meet growth in demand, ensure reliable delivery of  
          existing resources, and accommodate delivery of new resources.

          According to the CEC's 2003 IEPR, "(t)he state's bulk transmission  
          system needs major upgrades and improvements.  The broken  
          transmission permitting process in the state must be fixed so that  
          needed transmission investments can move forward."
















        In spite of the recognition of the CEC and other observers that  
        the public would benefit from new investments in the transmission  
        grid, little progress has been made in implementing major  
        transmission improvements in many years.  Electric restructuring  
        has complicated the question of who's responsible for transmission  
        planning, who should pay for transmission improvements, and who  
        will benefit.

        The Independent System Operator (ISO) plans for and recommends  
        transmission projects within its control area, but the  
        responsibility for building lies with the transmission-owning  
        utilities, who must initiate projects and obtain approval from the  
        CPUC.  A significant share of the state's transmission grid is  
        publicly owned and outside the jurisdiction of the ISO or the  
        CPUC.  

        In response to the fact that no state agency was charged  
        specifically with planning for the future of the transmission  
        system as a whole, SB 1565 was enacted last year to require the  
        CEC to develop a strategic transmission plan.  The CEC has begun  
        to work on the issue as part of its IEPR process, although the  
        initial SB 1565 plan isn't due until this November.

        According to the author, the state is suffering from a lack of  
        direction on electric transmission infrastructure.   
        Notwithstanding the fact that most of the state's transmission  
        grid is now supposed to operate as an integrated system,  
        responsibility for planning and permitting transmission projects  
        is divided between a multitude of federal, state and local  
        agencies, as well as private corporations, who either own or  
        manage pieces of the grid.

        According to the CEC, continuing urban expansion within California  
        has increased public opposition to the siting and development of  
        new bulk transmission lines.  Long-term planning for, and  
        designation of, transmission corridors would help to alleviate  
        this problem.  As part of the SB 1565 process, the CEC will  
        identify and evaluate potential transmission corridors to  
        accommodate future siting and construction of needed transmission  
        lines.  However, the CEC does not now have the authority to  
        formally designate such corridors to ensure that they will be  
        available when needed. 

                                      COMMENTS
         









              1)   TCZ idea originates from 2004 IEPR update recommendation.    
               According the CEC's recent report, there isn't a  
               comprehensive transmission planning process that encompasses  
               both the publicly and privately owned lines that make up the  
               state's transmission grid.  The CEC report found that the  
               state has no formal process to plan for transmission  
               corridors well in advance of need (and individual project  
               applications) so that needed land or easements can be  
               acquired by utilities.  The CEC report recommended  
               legislation to give them authority to formally designate  
               TCZs, which led to this bill.

               The CEC anticipates that, given the designation of TCZs,  
               utilities will acquire rights of way for potential future  
               lines ahead of time, at a lesser cost.  However, utilities  
               only spend their customers' money, so unless they have an  
               interest in speculative investment in real estate, they will  
               only do this if the CPUC assures recovery of land acquisition  
               costs from ratepayers.  It's unclear how the CPUC would  
               determine the reasonableness of such expenditures without  
               knowing when or if a transmission line will be constructed,  
               so this aspect of the CEC's vision may be infeasible in  
               practice.  It may also require a change in CPUC policy, which  
               currently limits utilities to hold transmission property for  
               future use for five years.

              2)   Relationship to CPUC process for approving individual  
               transmission projects.   Just as a local zoning ordinance does  
               not approve specific developments, the designation of a TCZ  
               pursuant to this bill would not constitute approval in whole  
               or in part of any specific transmission project, nor would  
               TCZ designation substitute for any of the federal, state or  
               local permits required to construct a transmission line  
               itself.  Similarly, designation of a TCZ would not give  
               eminent domain authority to a project proponent, or justify  
               condemnation of specific properties necessary to accommodate  
               the construction of a transmission line.  Those procedures  
               follow an application to construct a transmission line with  
               the relevant permitting agencies, which is not the CEC.  
          
              3)   Preemption of local land-use authority.   Land use is a  
               state police power which, with a few exceptions, has been  
               delegated to cities and counties.  Some examples of the state  
               retrieving land-use authority from locals within specified  
               geographical areas are the Coastal Commission, the San  









             Francisco Bay Conservation and Development Commission, the  
             Delta Protection Commission, and the Tahoe Regional Planning  
             Agency (created by interstate compact).  

             Examples of state preemption of locals by topic, rather than  
             geography, are state laws limiting development adjacent to  
             airports (Airport Land Use Commission law), seismic hazard  
             zones (Alquist-Priolo Act) and mineral deposits (Surface  
             Mining and Reclamation Act).  

             This bill gives the CEC authority to preempt local land use  
             authority via the designation of a TCZ.  For this reason, the  
             League of California Cities opposes this bill.  The League  
             also objects to provisions requiring cities to rely on the  
             CEC's EIR and incorporate the TCZ into local land-use plans  
             without regard to impacts on other elements of the plan.

            4)   Autonomy of charter cities vs. state police power.   Of  
             California's 478 incorporated cities, 108 are "charter  
             cities," as opposed to "general law" cities.   Charter cities  
             include the state's largest cities - Los Angeles, San Diego,  
             Fresno, San Jose, San Francisco, Oakland, Sacramento.  

             Under the California Constitution (Section 5 of Article XI),  
             charter cities are entitled to more autonomy than general law  
             cities.  City charters adopted pursuant to the Constitution  
             supersede all inconsistent laws (e.g. state laws) with  
             respect to "municipal affairs."  Thus, charter cities are  
             permitted to regulate "municipal affairs" without  
             interference from the state.  

             So, what's a "municipal affair" as opposed to some other  
             affair subject to general law?  Case law has tempered charter  
             city autonomy by drawing a line between "municipal affairs"  
             and "issues of statewide concern," which are governed by  
             state law.  (See, e.g., California Federal Savings and Loan  
             Association v. City of Los Angeles (1995) 11 Cal. 4th 342.)  

             In its findings, this bill indicates that "orderly planning  
             and development of needed high-voltage electric transmission  
             lines through the designation of transmission corridor zones  
             is an issue of statewide concern." (emphasis added)











              5)   Truncated CEQA process.   This bill doesn't explicitly say  
               the designation of a TCZ is subject to CEQA, but it does  
               require the preparation of an EIR (or an environmental  
               document if the CEC's TCZ review process is certified as the  
               functional equivalent of CEQA by the Secretary for Resources)  
               within one year of receipt of a TCZ application.  Further,  
               the bill requires cities and counties to use the CEC EIR as a  
               "program EIR" (a term defined in the CEQA guidelines, but not  
               in statute).

               The one-year deadline for the EIR may be infeasible for a  
               couple reasons.  First, the clock starts ticking upon receipt  
               of an application.  This is an unwise trigger, as an initial  
               application could be a completely inadequate basis to begin  
               CEQA review.  At a minimum, the clock should not start  
               ticking until the CEC has determined an application complete  
               and adequate.

               Second, the myriad local, state and federal agencies with  
               responsibilities to contribute to the EIR process, as well  
               other interested parties, may not have adequate time to  
               participate in the CEC's review if it's abruptly ended on the  
               365th day after application regardless of the state of  
               review.

               Also, it isn't clear what happens if the CEC misses the  
               deadline.  The bill should clarify that a TCZ will not then  
               be deemed approved and should permit the CEC to extend the  
               deadline if circumstances warrant.  Alternatively,  the author  
               and the committee may wish to consider  whether the deadline  
               should be eliminated.  It seems unnecessary in light of the  
               fact that the CEC may be the sponsor, or at least an  
               enthusiastic recipient, of TCZ applications, and will likely  
               process them as quickly as it can.

              6)   Double referral.   This bill has been referred to the  
               Senate Local Government Committee in addition to this  
               committee.

                                        POSITIONS
           
           Sponsor:
           
          Author










         Support:
         
        California Chamber of Commerce
        Sempra Energy

         Oppose:
         
        League of California Cities
        Southern California Edison

        

        Lawrence Lingbloom 
        SB 1059 Analysis
        Hearing Date:  April 5, 2005