BILL ANALYSIS
AB 1348
Page 1
Date of Hearing: May 18, 2005
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Judy Chu, Chair
AB 1348 (Runner) - As Amended: May 2, 2005
Policy Committee:
UtilitiesVote:11-0
Urgency: No State Mandated Local Program:
Yes Reimbursable: No
SUMMARY
This bill:
1)Authorizes a demonstration project, with specified parameters,
at the Antelope Valley Fairgrounds to determine the savings
from energy efficiency measures to reduce overall demand and
installing a photovoltaic (PV) solar energy system to reduce
peak energy demand.
2)Requires the electrical corporation serving the fairgrounds
(Southern California Edison), to file with the Public
Utilities Commission (PUC) a tariff providing for an incentive
rate specific to the demonstration project.
3)Requires the fairgrounds to submit biennial status reports and
a final report on the project to the PUC and the Legislature.
FISCAL EFFECT
Minor absorbable costs for the PUC to review and adopt the
required tariff.
COMMENTS
Purpose . The author indicates this bill is intended to create a
demonstration project allowing the Antelope Valley Fairgrounds
to install new energy efficiency systems and a new PV energy
system under a specially designed tariff that will allow the
fairgrounds to recoup the costs of a 630 kW solar energy system.
The demonstration project will be used to test the durability of
the systems and the effectiveness of combining large PV systems
AB 1348
Page 2
with modern energy efficiency technologies.
Analysis Prepared by : Chuck Nicol / APPR. / (916) 319-2081