BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 728
                                                                  Page  1

          Date of Hearing:   April 25, 2005

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                               Lloyd E. Levine, Chair
             AB 728 (Negrete McLeod) - As Introduced:  February 17, 2005
           
          SUBJECT  :   Electricity: biogas digester customer-generators: net  
          metering.

           SUMMARY  :   Deletes a sunset provision in a statute that allows  
          net energy metering for customer-owned electric generation  
          projects fueled by manure methane production.   Specifically,  
           this bill  :  

          1)Deletes all references to a pilot project in the code section  
            that allows net energy metering for customer-owned biogas  
            digester electric generation projects fueled by manure methane  
            production.

          2)Raises the current cap on size of an eligible biogas digester  
            customer-generator from 1 megawatt to 10 megawatts.

          3)Removes a cap on the total amount of load within an electrical  
            corporation's service territory that would be eligible for net  
            metering of biogas digester customer-generators.

          4)Deletes a sunset date of January 1, 2006 contained in the  
            provision that allows net energy metering for customer owned  
            electric generation biogas digesters.

           EXISTING LAW  :

          1)Creates a pilot project to allow for net metering of eligible  
            biogas digester customer-generators, which sunsets on January  
            1, 2006.

          2)Requires every electrical corporation to establish a  
            net-metering tariff for eligible biogas digester  
            customer-generators.

          3)Caps the size of an eligible biogas digester  
            customer-generator at one megawatt.

          4)Caps the total amount of load within an electrical  
            corporation's service territory that would be eligible for net  








                                                                  AB 728
                                                                  Page  2

            metering of biogas digester customer-generators at 5  
            megawatts.

           FISCAL EFFECT  :   Unknown.


           COMMENTS  :   According to the author's office, the purpose of  
          this bill is to delete a sunset on the net metering program that  
          permits dairies to offset the amount of electricity they  
          purchased with the amount of electricity generated by a customer  
          owned generation unit, which converts methane gas from manure  
          into electricity. These units are referred to biogas digestion  
          generators.


          1)  Background  : In 2001, the Legislature passed SBX1 5(Sher),  
          Chapter 7, Statutes of 2001, which appropriated $15 million for  
          grants for pilot projects designed to encourage the development  
          of biogas digestion power production technologies.

          In 2002, the Legislature passed AB 2228 (Negrete McLeod),  
          Chapter 845, Statutes of 2002, which created a pilot project to  
          permit net metering for customer-owned electric generation  
          projects fueled by manure methane production. The bill limited  
          the size of eligible biogas digesters to units that produce one  
          megawatt or less and the total amount of generation that would  
          be eligible to have a net meter to no more than 5 megawatts in  
          each service territory. 

          AB 2228 limited the qualified projects to those that are less  
          than one megawatt in part because net meter customer generation  
          cannot be scheduled by the electric utility. The utility thus  
          must take the power when it is produced, whether they need it at  
          that moment in time or not. The electric utility can easily  
          adapt to small amounts of unscheduled load coming onto the grid  
          at any time, but the utility may have reliability problems if  
          they cannot schedule larger generators. 

          The pilot project was funded by the appropriation in SBX1 5 and  
          had a sunset date of January 1, 2006.  According to the  
          sponsors, since the pilot project was put into place, 5  
          customers have installed biogas digester generators and are  
          operating under the net-metering tariff. Another 8 customers are  
          in the process of constructing biogas digester generators. The  
          entire $15 million appropriation has been spent.








                                                                  AB 728
                                                                  Page  3


          2)  What is net metering  : Under net metering, the electric  
          utility is required to buy back any electricity generated by a  
          customer-owned generator as measured by an electric meter that  
          can measure the flow of electricity in both directions.  When  
          the customer is generating excess power, the electricity not  
          being used passes through the meter and is distributed to the  
          electricity grid.  At the end of the year, the electric  
          corporation calculates the amount of electricity distributed to  
          the grid by the customer and reduces the customer's annual bill  
          by the amount of electricity generated by the customer  
          multiplied by the utility's standard generation costs. 

          3)  Results from the pilot project  : AB 2228 did not contain  
          stated goals of the pilot project or require a report to be  
          conducted that summarizes the project to determine the project's  
          effectiveness. Consequently, no data have been compiled to  
          determine the impacts the pilot project has had in efforts to  
          reduce emissions from dairies, on the electricity grid's  
          reliability and safety, or on to ratepayers. Given the fact that  
          none of this critical information has been prepared,  the  
          committee may want to consider amending the bill to, instead of  
          deleting the sunset and eliminating or raising the existing  
          caps, extend the current pilot project until 2010 and require a  
          report to the Legislature detailing: 1) the effectiveness of the  
          program in reducing air emissions, 2) the impacts the program  
          has on grid reliability and safety, and 3) the cost and benefits  
          the program imposes on other ratepayers  . 


           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Inland Empire Utilities Agency (Sponsor)
          Chino Basin Coalition (CBC)
          Milk Producers Council (MPC)
          Southern California Edison (If Amended)

          Western United Dairymen (Sponsor) 

           Opposition 
           
          Pacific Gas & Electric (Oppose Unless Amended)
           








                                                                 AB 728
                                                                  Page  4

          Analysis Prepared by  :    Edward Randolph / U. & C. / (916)  
          319-2083