Date of Hearing: August 4, 2004
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Judy Chu, Chair
SB 1565 (Bowen) - As Amended: June 24, 2004
Policy Committee: Natural
ResourcesVote: 6-2
Utilities 12-0
Urgency: No State Mandated Local Program:
No Reimbursable:
SUMMARY
This bill requires the California Energy Commission (CEC) to
include in its biennial Integrated Energy Policy Report (IEPR) a
strategic plan for the state's electric transmission grid that
identifies actions to implement investments needed to ensure
reliability and to meet future load growth.
FISCAL EFFECT
Minor absorbable costs for the CEC to incorporate the additional
information into the IEPR.
COMMENTS
Purpose . SB 1389 (Bowen)--Chapter 568/Statutes of 2002, which
created IEPR, does not include transmission planning as an
integral component. This bill seeks to solve the problem by
including the requirement that the CEC develop a strategic plan
for the state's electric transmission grid to be completed in
time for the November 1, 2005 IEPR.
Analysis Prepared by : Chuck Nicol / APPR. / (916) 319-2081