BILL ANALYSIS                                                                                                                                                                                                    




                                                                  SB 1269
                                                                  Page A
          Date of Hearing:  June 24, 2002

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                              Roderick D. Wright, Chair
                     SB 1269 (Peace) - As Amended:  June 20, 2002

           SENATE VOTE    24-14
           
          SUBJECT  :  Powerplant site and facility certification.

           SUMMARY  :  Modifies power plant construction and certification  
          policies of the California Energy Commission (CEC).   
          Specifically,  this bill  :   

          1)Allows CEC to revoke a power plant certification if, in the  
            absence of good cause, a project owner does not commence  
            construction of the project within 12 months of certification  
            by CEC.

          2)Requires a project owner to submit construction and operation  
            milestones to CEC within 30 days after project certification,  
            and failure without good cause to meet those milestones is  
            grounds for revocation of the certification or imposition of  
            civil penalties.

          3)Specifies that "good cause" includes:

             a)   Circumstances beyond the control of project owner,  
               including administrative and legal appeals.

             b)   Good faith, albeit unsuccessful efforts to meet project  
               deadlines or milestones.

             c)   Missing of deadlines or milestones for reasons deemed  
               reasonable by CEC.

          4)Increases the maximum civil penalties per violation by  
            $25,000<1> that can be imposed for false statements on a  
            permit application, or failure to comply with the conditions  
            of its approval.

          ---------------------------
          <1> This bill also increases the per-day civil penalty from  
          $1000 to $1500 per day, which penalty may also be imposed in  
          addition to the civil penalty imposed per violation. 









                                                                  SB 1269
                                                                  Page B
          5)Requires a project owner to begin construction of a project  
            within 12 months after the project is certified by CEC, the  
            clock beginning to run after all accompanying project permits  
            are final and administrative and judicial appeals have been  
            completed.

          6)Requires CEC to extend the start of construction an additional  
            24 months if the project owner reimburses CEC for its costs of  
            licensing the project.

          7)Authorizes CEC to transfer the certification to the Consumer  
            Power and Conservation Financing Authority (CPA) if CPA  
            demonstrates to CEC that it is willing and able to construct  
            the project itself or in conjunction with another public or  
            private entity.

          8)Requires CPA to reimburse the original certificate holder for  
            its actual costs<2> if CEC issues a new certificate to CPA and  
            the original party does not participate in the new project.

          9)Allows a project owner to sell its license, which would  
            restart the 12-month clock<3> for the new project owner. 

          10)Specifies that power plant certification applications filed,  
            and deemed complete after January 1, 2003 are subject to the  
            certification process changes embodied in this bill.

          11)States legislative findings and declarations that it is  
            critical to condition the issuance of power plant  
            certification on prompt, continuous, good faith efforts to  
            construct the certified project within its original  
            construction schedule.  Further states the policy of the state  
            that, in the event a certificate holder fails to demonstrate  
            prompt, continuous, good faith efforts to construct new power  
            plants, CEC may revoke the certification of the original  
            project owner and issue a new certification to CPA. 

           EXISTING LAW  :

          ---------------------------
          <2> Costs reimbursable include major equipment and emission  
          offsets. 

          <3> Unless the new project owner is an affiliate of the original  
          certificate holder. 









                                                                  SB 1269
                                                                  Page C
          1)Requires CEC to certify sites and related facilities that are  
            required to provide a supply of electric power sufficient to  
            accommodate projected demand for power statewide.

          2)Authorizes CEC to amend the conditions of or revoke the  
            certification for any facility and to administratively impose  
            a civil penalty for a material false statement in the  
            application, or failure to comply with the terms of a  
            certification.  Civil fines of up to $50,000 per violation may  
            be imposed.

          3)Permits CPA to issue revenue bonds to augment electric  
            generating facilities and to ensure a sufficient and reliable  
            supply of electricity, offer financing incentives for  
            investment in cost-effective, energy-efficient appliances and  
            energy demand reduction, among other powers.

           FISCAL EFFECT  :  Unknown.

           COMMENTS  :   

          CEC licenses power plants 50 megawatts or larger.  Under the  
          existing regulatory scheme, a license issued by CEC to construct  
          and operate a power plant expires by operation of law five years  
          after its issuance.  In February 2001, the Governor issued  
          Executive Order D-25-01, which directed CEC to establish  
          "specific  performance milestones for both initiation of  
          construction within one year of certification, and for the  
          construction phase of the project.  Failure to begin  
          construction by the deadline or failure to perform in accordance  
          with the milestones without prior approval by the [CEC] based on  
          a showing of good cause shall constitute a forfeiture of the  
          certification."  

          CEC issued guidelines<4> to carry out the emergency executive  
          order, establishing pre-construction milestones to allow for the  
          ---------------------------
          <4> The order authorized CEC to suspend statutory requirements  
          and regulations that normally control its review and approval of  
          post-certification amendments to the extent that they would  
          prevent, hinder, or delay the prompt mitigation of the effects  
          of the emergency declared in the order.  The order further  
          provided that CEC may "take such action by order on a case by  
          case basis or by any other means, and is not required to adopt  
          regulations under the Administrative Procedures Act to implement  
          this order."








                                                                  SB 1269
                                                                  Page D
          start of construction within one year of certification.  The  
          guidelines require that the milestones be established and agreed  
          upon no later than 30 days after approval of the project.  The  
          executive order expired December 31, 2001. 

           Author's statement  

          The grant of a license to build a power plant in California is a  
          determination that the wider public benefit associated with a  
          reliable supply of electricity for the community more than  
          offsets the mitigated impacts of the plant on the community.  In  
          making such determinations, the state invests considerable  
          public resources in investigating and processing every  
          application to license a power plant, without discrimination.   
          To the extent, however, that the licensee can choose not to  
          exercise the privilege to construct, the state will have  
          invested public resources to further only a private speculative  
          purpose with no corresponding public benefit. 

           Recent power plant project developments

           Since March 1998, CEC has approved more than 30 power plant  
          projects, although not all plants approved will be built.  Three  
          large power plants, totaling 1,400 megawatts, came on line in  
          2001 and are producing electricity.  Another 684 MW from  
          "peaking" power plants were on line by early 2002.  In 2002, one  
          plant rated at 880 MW has come on line.  A total of 13 power  
          plants totaling 2,979 MW has come on line since 1998. 

          Last year, eight power plant projects that would have produced  
          an aggregate of 1590 megawatts were withdrawn.  Two projects  
          have been withdrawn this year that would have combined to  
          produce 680 megawatts. 

          It is unclear how many of these withdrawn projects and how many  
          previously contemplated power plant projects will not be  
          completed in the future due to the various factors affecting  
          development.  Most importantly, commercial and institutional  
          lenders have tightened lending practices in the energy sector  
          over the last several months.  As a practical matter, it is no  
          longer possible to obtain financing for a power plant unless the  
          project owner can produce contracts for the power output from  
          the new facility.  

           Power plant development issues 









                                                                 SB 1269
                                                                  Page E
           
          Last Monday, a coalition of environmentalists and Indian tribes  
          sued several federal government agencies in an attempt to stop  
          Calpine Corp. from building a 49-megawatt geothermal power plant  
          in a remote corner of Northern California.  The Fourmile Hill  
          project would desecrate a spiritual site important to several  
          tribes, according to the lawsuit filed by the Pit River Nation,  
          one of the tribes suing to overturn the Bureau of Land  
          Management's approval of the power plant.

          Sixteen big power-generating stations are under construction,  
          being expanded or planned on both sides of the border from  
          California to Texas -- the majority of them located in Mexico.   
          Air quality agencies and some environmental organizations are on  
          record in opposition to these plants, contending that companies  
          are saving millions of dollars by evading stringent emissions  
          controls and other regulations that would apply if the plants  
          were being built north of the border. 

          A deputy director of Mexico's Federal Electricity Commission was  
          recently quoted as saying, "Construction costs are low in  
          Mexico; at the border there is more availability of fuel than in  
          the rest of the country; and a company can receive a permit in  
          six to eight months.  That is why they are building here."

          Earlier this year, the Federal Energy Regulatory Commission  
          approved construction of a 215-mile gas pipeline extension from  
          Arizona to Tijuana to deliver the fuel from Canada and the  
          United States to power plants along the border.  The pipeline is  
          expected to be completed this summer. 

          In the last several weeks, U.S. Senators Barbara Boxer and Diane  
          Feinstein have attempted to reverse these trends by introducing  
          legislation to prohibit U.S.-produced natural gas from being  
          used in power plants in Baja until the plants comply with  
          California emissions standards.

           Technical amendment  

          The applicability of the revocation authority for failure to  
          construct in 25534(a)(4) of this bill applies only to projects  
          not "deemed complete" until after January 1, 2003.  But other  
          subdivisions creating deadlines and procedures do not expressly  
          associate the requirements with permit applications in that  










                                                                  SB 1269
                                                                  Page F
          status when this bill becomes effective.<5>  The author or the  
          committee may wish to consider amending this bill to make this  
          reference where clarification is needed.  

           REGISTERED SUPPORT / OPPOSITION  :

           Support 
           
          Coalition of California Utility Employees
          Mirant Americas Development Inc.
          Utility Consumers Action Network
           
            Opposition 
           
          None on file.


          Analysis Prepared by  :    Paul Donahue / U. & C. / (916) 319-2083  



























          ---------------------------
          <5> See, e.g., Section 25534 (c),(d),(g), (h), (i) and (j) in  
          this bill