BILL ANALYSIS                                                                                                                                                                                                    




                    Appropriations Committee Fiscal Summary
          
           ------------------------------------------------------------ 
          |                               |1143(Bowen)                 |
          |-------------------------------+----------------------------|
          |                               |                            |
          |-------------------------------+----------------------------|
          |Hearing Date:  5/14/01         |Amended: As Introduced      |
          |-------------------------------+----------------------------|
          |Consultant:  Lisa Matocq       |Policy Vote: E, U & C       |
          |                               |7-0                         |
          |                               |                            |
           ------------------------------------------------------------ 
          ____________________________________________________________ 
          ___
          BILL SUMMARY: 
          
          SB 1143 (1) requires the California Energy Commission (CEC)  
          to (1) perform an annual assessment of the state's need for  
          additional energy resources, as specified, and (2) prepare  
          a plan to increase renewable generation to 15% of the  
          state's total generation by 2006, and to 20% by 2010.

                              Fiscal Impact (in thousands)
           
          Major Provisions                     2001-02              2002-03          
            2003-04                Fund  
          
          Annual assessment          $1,200            $400             $ 400   
                          General
          CEC plan                        ---  Probably minor costs ---         
                      General

          
          STAFF COMMENTS:  This bill meets the criteria for referral  
          to the Suspense File. 

          SB 110 (Peace, Ch. 581, St. of 1999) eliminated the  
          integrated assessment of need requirement. 

          CEC staff indicate that preliminary cost estimates are $1  
          million one-time for data procurement, consulting, and  
          computer modeling, and staff costs of about $400,000  
          ongoing to prepare the annual assessment.  The costs for  
          the renewable generation plan are probably minor.  











          STAFF NOTES that the renewable generation plan is due "at  
          the earliest possible time".  The author and committee may  
          wish to consider (1) specifying, "?but not later than  
          December 31, 2002, or some other date, and (2) requiring  
          that the plan and annual assessment be submitted to the  
          Legislature and the Governor.