BILL ANALYSIS                                                                                                                                                                                                                   1
               1





             SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE
                            DEBRA BOWEN, CHAIRWOMAN
          

          SB 28X -  Sher                Hearing Date:  March 6, 2001   
               S
          As Amended:  March 5, 2001              FISCAL           B
                                                                       
            X
                                                                       
            1

                                                                       
            2
                                                                       
            8

                                   DESCRIPTION
           
          This bill contains a series of provisions intended to  
          accommodate increased construction and operation of power  
          plants.  Specifically, this bill:

                Siting provisions (Sections 6 and 8 through 12)

          1.With respect to the California Energy Commission's (CEC)  
            ordinary certification process for thermal power plants  
            50 megawatts and larger, limits the comment period for  
            local jurisdictions to 45 days following filing of an  
            application for initial comments, and 90 days for final  
            comments.

          2.Requires the CEC, in its written decision on a power  
            plant application, to discuss any public benefits from  
            the project (economic, environmental or reliability).

          3.Requires the CEC to adopt a regulation governing ex parte  
            contacts, which allows substantive contacts between  
            parties and CEC officials, but requires prompt disclosure  
            and a written summary of the contact.

          4.Provides that CEC siting decisions are subject to Supreme  
            Court review.  (Currently, CEC decisions track the appeal  
            process of California Public Utilities Commission (CPUC)  











                 decisions, which used to go directly to the Supreme  
                 Court.  The process applicable to the CPUC was changed to  
                 provide for lower appellate court review of adjudicatory  
                 decisions by SB 1322 (Calderon), Chapter 855, Statutes of  
                 1996.  This bill changes the CEC's process back to the  
                 way it was prior to the enactment of SB 1322.)

               5.Requires the CEC to issue final certification for  
                 "re-powering" projects within 180 days (Decisions on  
                 modifications to existing power plants are currently  
                 subject to a 12-month deadline).  For purposes of this  
                 section, "re-powering" means a project that: 

                 A)  Initial evidence suggests will not cause a  
                 significant adverse impact on the environment or the  
                 electrical system, will comply with applicable legal  
                 standards, and will make its output available to  
                 California.




































            B)  Is located within the boundaries of an existing power  
            plant and will not require significant additional  
            rights-of-way for transmission or fueling, but does not  
            necessarily replace the existing plant.

            C)  Will significantly and substantially increase the  
            efficiency of the project, on a per kilowatt-hour basis,  
            with respect to gas consumption, water use and discharge,  
            and air pollution.

            D)  Has a contract for an adequate supply of skilled  
            labor to construct, operate and maintain the plant.

            E)  Complies with CEC regulations regarding environmental  
            justice.

            With respect to re-powering projects, limits the comment  
            period for local, regional and state jurisdictions to 100  
            days.

            These provisions sunset on January 1, 2004.

          6.Extends the application of the four-month siting process  
            for temporary "peaker" power plants.  As established by  
            AB 970 (Ducheny), Chapter 329, Statutes of 2000, plants  
            had to be in service by August 1, 2001 to qualify.  This  
            bill extends the date 17 months, to December 31, 2002.

          7.Expands the application of the "peaker" process to allow  
            re-certification or replacement by a co-generation  
            facility within three years.  Under AB 970, simple-cycle  
            peakers were required to be replaced by combined-cycle  
            plants.

                  Air quality provisions (Sections 3, 4 and 5)

          1.Requires the Air Resources Board (ARB) to implement a  
            program for "expedited retrofit" of power plant pollution  
            controls.

          2.Requires ARB to implement an expedited statewide program  
            for "identification and banking" of emission reduction  
            credits for power plants and natural gas transmission  
            facilities.











               3.Requires each air district to adopt an expedited program  
                 for permitting of standby or distributed generation  
                 facilities and natural gas transmission facilities. 

               4.A)  Authorizes payment to air districts of mitigation  
                 fees for a new power plant in lieu of obtaining actual  
                 emissions offsets, when the owner or operator of the  
                 plant has shown that offsets are not available.  The  
                 mitigation fees are to be used for the Carl Moyer  
                 program, which provides grants to reduce NOx emissions  
                 from vehicles, or a similar program. 










































            B)  Authorizes posting of a bond or letter of credit  
            equivalent to the cost of required offsets for a new  
            power plant in lieu of obtaining actual offsets, whether  
            or not offsets are available.  If all required offsets  
            have not been obtained by the time the plant starts  
            operating, a share of the bond equal to the portion of  
            offsets not obtained is forfeited.  The use of forfeited  
            bonds is not specified.  

            C)  Requires the air district to hold a public hearing to  
            determine the appropriate amount of fees or bonds to be  
            paid in lieu of offsets.  The amount shall be sufficient  
            to obtain equivalent emission reductions. 

            D)  Authorizes the air district to suspend or limit these  
            provisions if it determines their application would  
            interfere with attainment or maintenance of air quality  
            standards, or if it determines adequate offsets are  
            available at a "reasonable" price.  

            E)  These provisions sunset on January 1, 2004.

                    Tax provisions (Sections 1, 2, 7 and 13)

          1.Allocates 100% of property tax revenues associated with  
            new generation projects to applicable local jurisdictions  
            by requiring property taxes from any new power plant,  
            co-generation, transmission or distribution facility that  
            would be locally assessed (i.e., non-utility) to be  
            allocated entirely to the county or city in which the  
            plant is located.  Also requires that tax rates be the  
            same as they would have been absent the addition of this  
            provision.

          2.Requires the CEC, in its final report on a power plant  
            application, to address whether increased property taxes  
            due to construction of the project are sufficient to  
            support local improvements and public services necessary  
            to serve the project.

                        Funding provisions (Section 14)

          Appropriates $54 million from the General Fund to the CEC  
          as follows:











               1.$50 million to increase rebates for clean, renewable  
                 distributed energy systems smaller than 10 kilowatts.

               2.$3 million to assist cities and counties with expedited  
                 review of power plant applications.

               3.$1 million for a study of shoreline water contamination  
                 in Huntington Beach.













































                                    BACKGROUND
           
          In 1974, in response to a previous energy crisis, the  
          Warren-Alquist Act established an exclusive process for  
          siting of thermal power plants 50 megawatts and larger.   
          The siting process was intended to provide comprehensive  
          environmental review and predictable, one-stop permitting  
          of applications.  It was also integrated with a planning  
          process that  was intended to guard against under or  
          overbuilding of power plants.

          The Act required the CEC to develop long-term forecasts of  
          state energy needs, which served as the basis for planning  
          and certification of individual power plants.  Since the  
          advent of electrical restructuring, the planning and siting  
          functions have been de-coupled, but the Act still grants  
          the CEC exclusive authority to certify power plants and  
          authorizes the CEC to override other state, local or  
          regional decisions and certify a power plant it determines  
          is required for "public convenience and necessity." 

          The construction of the CEC's siting review function in the  
          Warren-Alquist Act strikes a balance between project  
          applicants' interest in certainty and the public's interest  
          in environmental protection and prudent planning of  
          generation resources.  The CEC's  siting process is a  
          CEQA-equivalent project evaluation process and was intended  
          to be rigorous and comprehensive.  In approving a proposed  
          power plant, the CEC must find that the facility's  
          construction and operation is consistent with a variety of  
          environmental standards.

          This bill proposes a series of changes to air quality, CEC  
          siting, and property tax laws designed to encourage the  
          expedited siting of clean new generation in the state.  The  
          author notes that the package of proposals contained in  
          this measure are similar to many such proposals identified  
          by generators, the Governor's office, and other parties to  
          address the need for clean new generation in the state.   

                                     COMMENTS
           
           1.Talkin' 'bout My Generation.   In order to shorten the  
            review period for power plant applications, this bill  










                 limits the comment period for local jurisdictions to 45  
                 days following filing of an application for an initial  
                 list, and 90 days for a final list.  This is the primary  
                 "streamlining" provision for the ordinary certification  
                 process for new, permanent power plants.  

                 Currently, there is no uniform statutory local comment  
                 period, although AB 970 included a 100-day comment period  
                 for the six-month siting process it established for  
                 "environmentally benign" projects.  Representatives of  
                 local governments have commented that the 45/90 day  
                 timeframe is not adequate to provide appropriate review.   
                 They have suggested that review periods allotted to the  
                 CEC and other agencies also should be reduced, and that  
                 time limits be somehow linked to the size and complexity  
                 of the project.






































            At a minimum,  the author and the committee may wish to  
            consider  adopting a uniform standard for local review  
            (45/90, 100-day, or some compromise) that would apply to  
            each siting process.

           2.Tune-In, Turn-On, Re-Power.   Intuitively, it seems a  
            "re-power" project would be a conversion of an existing  
            unit to a newer, more efficient unit.  However, it is not  
            clear that this bill's re-power process is limited to  
            projects which convert existing generation units.   
            Arguably, an applicant could use this process to site a  
            new unit adjacent to an existing unit, with the intent of  
            operating both.   The author and the committee may wish to  
            consider  whether the definition of a re-power project  
            should be limited to prevent such a circumstance.

            In addition, the provision which requires the output of a  
            re-power project to "be made available to serve  
            electrical customers located within the state" is  
            probably ineffective in accomplishing its intent and  
            possibly counterproductive to a solution to the current  
            energy crisis.  An applicant could comply with the letter  
            of this provision by offering one percent of a plant's  
            output to in-state customers, even if that power was not  
            actually delivered.

            In addition, "California First" policies run the risk of  
            inviting similar defensive measures from other states.   
            California has long benefited, both in economic and  
            environmental terms, from seasonal exchanges of power  
            with neighboring states whose demand for electricity  
            peaks at different times than ours.  The electricity  
            generating infrastructure throughout the West has  
            developed with a recognition of the efficiencies of  
            mutually beneficial exchanges.  Balkanization of power  
            supplies would require each state to dramatically  
            increase its generating capacity.

             The author and the committee may wish to consider  whether  
            a more effective way to address frustrations with the  
            downsides of deregulation would be to require, as a  
            condition of accelerated regulatory treatment, that the  
            output of power plants be "dedicated to operation for the  
            benefit of California ratepayers."











                3.I'll Gladly Pay You Tuesday...   This bill proposes to  
                 allow the payment of mitigation fees for power plant  
                 emissions in lieu of obtaining actual offsets, as well as  
                 the banking of emission reductions, on a statewide basis.  
                  These instruments will facilitate off-site mitigation of  
                 on-site project impacts.  

                 This bill provides limited guidance as to the proximity  
                 or comparability of "in lieu" mitigation measures.    
                 Mitigation fees collected by air districts are to be used  
                 for the Carl Moyer program, which provides grants to  
                 reduce NOx emissions from vehicles, or a similar program.  
                  The provision which authorizes posting of a bond in lieu  
                 of obtaining actual offsets provides for the forfeiture  
                 of the bond if all required offsets have not been  
                 obtained by the time the plant starts operating, but does  
                 not specify what any bond proceeds may be used for.




































             The author and the committee may wish to consider  whether  
            the use of mitigation fees should be constrained with  
            respect to time, distance, pollutant, and/or source.  For  
            example, should nearby stationary sources emitting a  
            similar array of pollutants be the first priority?

            In addition, the intent of the bill is unclear regarding  
            the circumstances under which in lieu mitigation measures  
            are appropriate.  In proposed Health and Safety Code  
            Section 42314.3 (page 9), subdivision (a) says mitigation  
            fees should be paid when offsets are not available,  
            subdivision (b) allows a bond in lieu of offsets without  
            regard to the availability of offsets, and subdivision  
            (e) allows an air district to suspend or limit the in  
            lieu provisions when offsets are available at a  
            "reasonable" price.  The author and the committee may wish  
            to consider  adopting a uniform standard to govern when in  
            lieu measures may be substituted for obtaining offsets,  
            and clarifying that these in lieu provisions apply to new  
            power plants only.   Also, it is unclear whether  
            subdivisions (a) and (b) are intended to be alternatives  
            to one another, or whether subdivision (b) is intended to  
            be governed by subdivision (a).

           4.The Payoff Pitch.   This bill incorporates tax allocation  
            provisions similar to those contained in SB 30X (Brulte),  
            which provide for allocation of property tax revenues  
            associated with new generation projects entirely to the  
            county or city in which the plant is located.  SB 30X has  
            been referred to the Revenue and Taxation and Local  
            Government Committees.

            This provision applies to projects  placed in service  on  
            or after January 1, 2001, so it would apply to at least  
            nine projects which have already won approval from local  
            agencies and received final certification from the CEC,  
            but haven't been placed in service yet.  Presumably,  
            these projects adopted mitigation measures and won  
            approval relying on the existing tax allocation scheme.   
            If this provision is intended to reward communities that  
            don't obstruct a proposed power plant,  the author and the  
            committee may wish to consider  whether projects already  
            approved should qualify for the new tax allocation rules.











                 In addition, to the extent this provision is intended to  
                 serve as an incentive or a reward for local cooperation,  
                 it may be overly broad.  For example, it would apply to  
                 the proposed Metcalf Energy Center, even though necessary  
                 zoning changes for Metcalf were unanimously rejected by  
                 the San Jose City Council, if the CEC elects to override  
                 the city's decision and the project is ultimately built.   
                 Also, the bill does not tie the expenditure of any  
                 additional tax dollars to the specific location of the  
                 power plant.  This may be necessary to ensure that  
                 unincorporated areas of counties or neighborhoods of some  
                 larger cities would actually benefit from any property  
                 tax funds accruing to a county or city as a result of a  
                 new power plant.








































            Finally, under Section 16 of Article XVI of the  
            California Constitution, a redevelopment agency is  
            entitled to keep all property tax growth inside a project  
            area.  This bill says that the underlying city or county  
            would keep all property taxes associated with a new power  
            plant.  To avoid a clear conflict with the Constitution,  
             the author and the committee may wish to consider  adding  
            an exception to this bill for power plants within a  
            redevelopment project area.
           
          5.Generation First!  - On February 8, the Governor issued  
            the following Executive Orders related to construction  
            and operation of power plants:

            D-22-01 exempted from CEC review an increase in  
            production of less than 50 megawatts above existing  
            authorized levels between June and October, ordered the  
            CEC and other jurisdictions to expedite consideration of  
            power plant projects, ordered the State Water Resources  
            Control Board to take action to ensure that power plants  
            are not shut down as a result of thermal discharge  
            violations, and ordered the Department of Water Resources  
            (DWR) to contract, at reasonable rates, with power plants  
            that may have no other market.  D-22-01 expires on  
            December 31, 2001.

            D-24-01 ordered air districts to modify air permits for  
            power plants that provide power under contract to DWR to  
            ensure may operate without restriction.  Districts were  
            further ordered to require a mitigation fee for excess  
            emissions.  The ARB was required to modify the permits if  
            the districts failed to do so and to make its remaining  
            funding available for the purchase of "emissions offset  
            credits."  D-24-01 expires on December 31, 2001.

            D-25-01 ordered the CEC to expedite review of amendments  
            to existing power plants, ordered the CEC to impose  
            conditions to revoke a power plant's certification if  
            construction is not initiated within one year, authorized  
            the CEC to suspend applicable statutes and regulations to  
            accomplish these.  D-25-01 expires on December 31, 2001.

            D-26-01 ordered local jurisdictions to shorten the EIR  
            review period to seven days for power plants not subject  










                 to CEC review (i.e., under 50 MW) if they are proposed to  
                 be on-line by this summer.  The CEC was ordered to  
                 expedite review of emergency power plants that can be  
                 on-line by July.  AB 970's four-month process for siting  
                 of peakers was extended to August 31, 2002 and statutory  
                 restrictions on the process were suspended.   Finally,  
                 investor-owned utilities were required to complete  
                 transmission interconnection studies for emergency power  
                 plants within seven days.  D-26-01 expires on December  
                 31, 2001.

                 D-27-01 ordered the Department of Parks and Recreation to  
                 make its remaining appropriated funds available to the  
                 CEC for the payment of bonuses for power plants brought  
                 on-line prior to July 1, 2001.







































           6.Sunsets.   To the extent provisions of this bill are  
            intended to address a near-term need for additional  
            generation, it may be appropriate to sunset them.   
            Currently, the fee in lieu and re-power sections of this  
            bill sunset on January 1, 2004.   The author and the  
            committee may wish to consider  whether any other sections  
            should be subject to a sunset.

                                    POSITIONS
           
           Sponsor:
           
          Author

           Support:
           
          California Chamber of Commerce

           Oppose:
           
          None on file



          Lawrence Lingbloom 
          SB 28X Analysis
          Hearing Date:  March 6, 2001