BILL ANALYSIS
Appropriations Committee Fiscal Summary
2838 (Canciamilla)
Hearing Date: 8/13/02 Amended: 8/5/02
Consultant: Lisa Matocq Policy Vote: E, U & C
8-0
____________________________________________________________
___
BILL SUMMARY:
AB 2838 requires the Public Utilities Commission (PUC) to
issue a decision on a water utility company's application
for a general rate increase, within a certain time period,
as specified. It also requires the PUC to establish a
schedule to review the rates of water corporations every
three years.
Fiscal Impact (in thousands)
Major Provisions 2002-03 2003-04
2004-05 Fund
PUC Potential costs of $445 in 2002-03, and
Special*
$891 annually thereafter. Costs should
be
offset by fee revenues.
*Public Utilities' Reimbursement Account (PURA)
STAFF COMMENTS:
The bill provides that if the PUC fails to issue a decision
within the specified time period, the applicant may be
granted interim rates (current rate, plus inflation).
These rates would be subject to refund, pending the final
decision.
There is no specific schedule for reviewing water rates
under current law. There are 10 large water companies with
a total of 64 districts. Over the past four years, the PUC
has reviewed an average of about 10 per year, and this bill
would require them to review approximately 20 per year,
thereby doubling their workload. Increased costs to the
PUC are estimated at $445,000 in 2002-03, and $891,000 in
2003-04 and annually thereafter. PURA revenues are
derived from an annual fee imposed on public utilities.
Therefore, any increased costs should be offset by
increased fee revenues.