BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 1529
                                                                  Page  1

          Date of Hearing:  January 14, 2002

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                              Roderick D. Wright, Chair
                   AB 1529 (Wyman) - As Amended:  January 10, 2002
           
          SUBJECT  :  Transmission and gas lines.

           SUMMARY  :  Requires the California Public Utilities Commission  
          (CPUC) to act as expeditiously as possible, but in no event  
          exceed the timelines provided in current law, when reviewing or  
          acting upon an application for a Certificate of Public  
          Convenience and Necessity (CPCN) authorizing construction of any  
          electric plant, line, or extension, or gas plant, line, or  
          extension.

           EXISTING LAW  :

          1)Requires electrical and gas corporations to obtain from CPUC a  
            CPCN prior to construction of  any electric plant, line, or  
            extension, or gas plant, line, or extension.

          2)Requires CPUC, when granting a CPCN, to give consideration to  
            the following factors:

             a)   Community values;

             b)   Recreational and parks areas;

             c)   Historical and aesthetic values;

             d)   Influence on environment.

          3)Pursuant to the Permit Streamlining Act, requires CPUC, as the  
            lead agency of the project, to approve or disapprove the  
            project within 180 days (six months) from the certification of  
            an environmental impact report (EIR), or within 60 days (two  
            months) if a negative declaration is completed and adopted for  
            the project or a determination that the project is exempt from  
            the California Environmental Quality Act (CEQA).

          4)Allows additional time if there are compelling circumstances  
            and the project applicant consents.

           FISCAL EFFECT  :  Unknown.








                                                                  AB 1529
                                                                  Page  2


           COMMENTS  :

           The Need for Additional Electric and Gas Infrastructure
           
          Despite a significant increase in electricity demand in recent  
          years, California has not built any major transmission projects  
          in more than a decade.  The lack of transmission upgrades has  
          created transmission congestion, or "bottlenecks," which have  
          exacerbated the state's energy woes and contributed to the  
          increase in the price of electricity.  The state's gas  
          infrastructure has also suffered from a lack of investment,  
          which has contributed to an increase in the cost of natural gas.  
           Much of California's natural gas supply comes from out of  
          state.  Improvements to the natural gas infrastructure would  
          help reduce gas prices and reduce our reliance on out of state  
          gas.

           The CPCN Process
           
          During the CPCN process, CPUC considers an array of factors,  
          including cost, reliability, need, and environmental impact.   
          The environmental issues are addressed pursuant to CEQA.  CEQA  
          requires CPUC  to prepare an initial study to assess the  
          project's impact on the environment, and to issue a negative  
          declaration if the initial study shows no significant effects.   
          Most electric transmission and gas distribution line projects  
          are large in scale and cause significant environmental impacts,  
          in which case CPUC is required to prepare an EIR.

          The CPCN process is subject to the Permit Streamlining Act,  
          which sets deadlines for public agencies to act on proposed  
          projects.  This bill requires CPUC to act as expeditiously as  
          possible in reviewing and acting upon electric and gas related  
          CPCNs, but does not change any of the current statutory  
          deadlines.

           REGISTERED SUPPORT / OPPOSITION :   

           Support 
           
          None on file.

           Opposition 
           








                                                                  AB 1529
                                                                  Page  3

          None on file.

           
          Analysis Prepared by  :    Joseph Lyons / U. & C. / (916) 319-2083