BILL ANALYSIS                                                                                                                                                                                                              1
          1





                SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE
                               DEBRA BOWEN, CHAIRWOMAN
          

          AB 57 -  Wright                                   Hearing Date:   
          May 21, 2002               A
          As Amended:         May 15, 2002             FISCAL       B
                                                                        
                                                                        5
                                                                        7
                                                                        
                                      DESCRIPTION
           
           Existing law  requires that rates demanded or received by an  
          investor-owned utility (IOU) be just and reasonable and assigns  
          responsibility for ensuring the reasonableness of such rates to  
          the California Public Utilities Commission (CPUC).

           Existing law  (AB 1X (Keeley), Chapter 4, Statutes of 2001)  
          authorizes the Department of Water Resources (DWR) to procure  
          the "net short" requirements of electric utilities.  Pursuant to  
          AB 1X, DWR is prohibited from contracting for electricity after  
          December 31, 2002.  DWR may continue to administer pre-existing  
          contracts and sell electricity after that date.

           This bill  establishes a process under which an IOU may be  
          assured that its electricity procurement expenses will be  
          recoverable in customer rates, if that procurement is conducted  
          consistent with a CPUC-approved procurement plan.

          Specifically,  this bill  :

          1.Requires the CPUC to allocate electricity provided by DWR  
            among the IOUs.

          2.Requires each IOU to file - and the CPUC to review and accept,  
            modify, or reject - a procurement plan specifying the date the  
            IOU intends to resume procurement and enabling the IOU to  
            fulfill its obligation to serve its customers at just and  
            reasonable rates, eliminating the need for after-the-fact  
            reasonableness reviews (with specified exceptions), and  
            ensuring timely recovery of prospective procurement costs.

          3.Requires the procurement plan to be based on one or more of  











            the following reasonableness standards: 

            a.        An approved competitive bid-based procurement  
            process. 

             b.        A performance-based incentive mechanism that shares  
               procurement risks and rewards between an IOU and its  
               customers.  

             c.        Objective standards and review to determine the  
               recoverability of procurement transactions prior to their  
               execution.

          4.Requires the CPUC to establish balancing accounts for each IOU  
            to track the differences between recorded revenues and  
            procurement costs incurred, and to review the account  
            semiannually, and adjust rates or issue refunds to promptly  
            amortize the accounts.  Until January 1, 2006, adjustment is  
            required whenever an account is under- or over-collected by  
            more than five percent of the IOU's actual recorded generation  
            revenues for the prior calendar year.

          5.Requires the CPUC to provide for periodic review and  
            modification of procurement plans.

          6.Authorizes the CPUC to contract out for risk management and  
            strategy advisors.

          7.Requires the CPUC, prior to its approval of any divestiture of  
            generation assets owned by an IOU, to determine the impact of  
            the divestiture on the IOU's procurement rates and allows  
            approval only if the CPUC determines the divestiture will  
            result in net ratepayer benefits.  Generally makes procurement  
            necessitated by future generation asset divestiture ineligible  
            unless its cost is less than the recent historical cost of the  
            divested assets.

          8.Allows an IOU with less than 500,000 retail customers to apply  
            for an exemption from these provisions.

          9.Appropriates $600,000 to the CPUC from the Utility  
            Reimbursement Account.

          10.                                Is an urgency bill.











                                      BACKGROUND
           
          Existing law requires that rates demanded or received by public  
          utilities be just and reasonable and assigns responsibility for  
          ensuring the reasonableness of rates to the CPUC.  This  
          authority is a foundation of utility regulation, dating back to  
          the establishment of the CPUC's predecessor, the Railroad  
          Commission, in 1909.  The power to review expenses that are  
          recoverable from utility ratepayers was judged necessary to  
          protect the public from the exercise of monopoly powers.

          When the electric market was deregulated, the CPUC required IOUs  
          to buy and sell from the Power Exchange (PX), which initially  
          offered only day-ahead and hour-ahead markets.  In 1999, the PX  
          began facilitating forward contract transactions in its block  
          forward market.  Purchases from the PX were deemed "per se  
          reasonable" by the CPUC.

          As a result of market conditions during the energy crisis,  
          long-term, bilateral contracts were viewed as an attractive way  
          to stabilize volatile and high prices.  After-the-fact review of  
          the reasonableness of these contracts by the CPUC has been  
          viewed by IOUs as a deterrent to entering such contracts.

          In 2000, the CPUC began to authorize IOUs to purchase power  
          through privately-negotiated bilateral contracts.  By August  
          2000, the CPUC had authorized bilateral contracts equivalent to  
          the average power purchase needs (net short) of each IOU.  The  
          average net short requirement is substantially less than the  
          peak net short requirement during periods of high demand.  The  
          CPUC then indicated that contracts for a price more than 5%  
          above the average of comparable transactions would be subject to  
          reasonableness review.

          After the adoption of this standard, the CPUC twice proposed  
          price benchmarks for forward contracts which, if met, would  
          exempt the IOU from subsequent reasonableness review.  Each  
          time, the general price benchmark for a five-year, 7-by-24  
          contract was proposed to be six cents per kilowatt hour.   
          Specific price benchmarks have been criticized for creating a  
          target that no seller would go below.  The CPUC never adopted a  
          specific price benchmark. 











          CPUC review of contracts presents the possibility that recovery  
          of certain contract expenses will be disallowed if the contract  
          is judged to be an unreasonable deal (e.g. unjust price or  
          inappropriate conduct).  On the other hand, it has been thought  
          that, after the end of the rate freeze, if the contract is a  
          great deal, the IOU gets no reward beyond the ability to recover  
          its costs.  The IOUs have noted that these circumstances place  
          all the downside risk on them and create a clear disincentive to  
          enter into long-term contracts.  The competing argument is that  
          if IOUs are permitted to pass their power purchase costs on to  
          their customers unconditionally, they have little incentive to  
          negotiate the best deal.

          The use of forward contracts by IOUs has been very limited -  
          none of the IOUs forward contracted to the level authorized by  
          the CPUC.  Since the passage of AB 1X, the net short  
          requirements of each IOU has been procured by DWR.  Pursuant to  
          AB 1X, DWR is prohibited from contracting for electricity after  
          December 31, 2002.  DWR is allowed to continue to administer  
          pre-existing contracts and sell electricity after that date.

                                       COMMENTS
           
           1)Does the schedule work?   Assuming the objective is that IOUs  
            will resume procurement no later than January 1, 2003, the  
            schedule outlined in this bill (with the restoration of the  
            language described in Comment 4) leaves little margin for  
            error.  First, the CPUC must divide DWR-procured power among  
            the IOUs so each knows how much more power they'll need to  
            procure.  Under the best-case scenario, this controversial  
            task could be complete by the time the bill is enacted.  Next,  
            each IOU has 60 days to file a procurement plan, including a  
            proposed commencement date for procurement.  Then, the CPUC  
            needs a certain amount of time to review and approve the  
            plans.  Finally, CPUC approval must be at least 90 days prior  
            to the proposed commencement date.

            Under this schedule, assuming allocation of DWR power is  
            complete by the time the bill is enacted, the bill is passed  
            and signed by June 5, and the CPUC approves the plans only 60  
            days after they are filed, the proposed schedule would  
            conclude, with IOU procurement commencement, on January 1,  
            2003, in the nick of time.  Of the 210 days preceding the  
            commencement date, 150 are allocated to IOUs for preparation  










            of plans and notice.

            The CPUC has initiated a procurement rulemaking consistent  
            with this bill, anticipating its enactment.  Under the current  
            schedule in that proceeding, and the schedule in this bill, it  
            appears unlikely that the January 1, 2003 goal will be met.   
            Overlaying the procedural schedule are other uncertainties  
            affecting IOUs' resumption of procurement, such as  
            creditworthiness and bankruptcy.

             The author and the committee may wish to consider  whether this  
            schedule is achievable, whether adjusting the deadlines in the  
            bill can make it achievable, and what happens if it is not  
            achieved.

           2)Balances and triggers.   This bill requires the CPUC to  
            establish balancing accounts for each IOU to track the  
            differences between recorded revenues and procurement costs  
            incurred, to review the account semiannually, and to adjust  
            rates or issue refunds to "promptly amortize" the accounts.  

            Until January 1, 2006, adjustment is required whenever an  
            account is under- or over-collected by more than five percent  
            of the IOU's actual recorded generation revenues for the prior  
            calendar year.  This provision is intended to assure creditors  
            that IOUs won't be required to carry excessive procurement  
            debt during a "rehabilitation" period (or retain excessive  
            procurement profit).  By way of example, five percent of  
            Southern California Edison's 2001 recorded generation revenues  
            is approximately $325 million.

            If applied to current rates and power costs, this mechanism  
            may well lead to refunds or rate decreases.  However, in the  
            future, it could compel the CPUC to increase rates.  It is  
            unclear whether the bill, when the five percent threshold is  
            exceeded, would require the account balance to be amortized to  
            zero, or just to under five percent.   The author and committee  
            may wish to consider  amending the bill to clarify this  
            provision.

           3)Related legislation affecting IOU procurement practices.   SB  
            532 (Sher) establishes a "Renewable Portfolio Standard" for  
            retail electricity suppliers which would require IOUs to  
            procure renewable power, or credits, sufficient to meet the  










            bill's objective of achieving a level of renewable power  
            equivalent to 20 percent of statewide of electricity  
            consumption by 2010.  SB 532 failed passage on a 7-3 vote in  
            the Assembly Utilities and Commerce Committee on September 6,  
            2001 and is pending reconsideration.

            SB 1885 (Bowen) requires an IOU, as a part of its obligation  
            to serve the public, to obtain adequate supplies of   
            electricity to meet the needs of its customers.  This bill  
            finds that because of extraordinary circumstances, DWR was  
            temporarily charged with acquiring adequate electricity  
            supplies, and that the public interest is served by returning  
            the electric supply obligation to the utilities as soon as  
            possible.  SB 1885 is pending on the Senate Floor.

            Procurement for IOU customers will also be affected by the  
            pending sunset of DWR's power purchasing authority.  While AB  
            57 addresses the IOUs' needs with respect to resuming  
            procurement, the important matter of how DWR will transition  
            out of its procurement role remains to be addressed.

           4)Prior hearing.   This bill was heard, and approved on a 5-3  
            vote, by this committee on July 10, 2001.  The bill since has  
            been completely rewritten pursuant to a consensus-based  
            negotiation between IOUs, the CPUC, consumer groups, the  
            author's office, members of this committee and others.




























           5)Technical amendment.   The May 15 amendments to the bill strike  
            critical requirements and deadlines for IOUs to file, and for  
            the CPUC to adopt, procurement plans.  According to the  
            author's office, striking this language was a technical error.  
              The author and the committee may wish to consider  restoring  
            these requirements as follows:

               On page 4, line 8, after "plan." insert:

            Each electrical corporation shall file a proposed procurement  
            plan with the commission not later than 60 days after the  
            commission specifies the allocation of electricity.  The  
            proposed procurement plan shall specify the date the  
            electrical corporation intends to resume procurement of  
            electricity for its retail customers, consistent with its  
            obligation to serve, which shall be referred to for purposes  
            of this subdivision as the "proposed commencement date."  The  
            commission shall review and adopt a procurement plan as  
            specified in subdivisions (b), (c), and (d) no later than 90  
            days prior to the proposed commencement date.

            (These deadlines would need to be revised if the committee  
            desires to adjust the schedule per Comment 1.)
                                           
                           ASSEMBLY VOTES (Prior Version)
           
          Assembly Floor                     (65-0)
          Assembly Appropriations            (14-0)
          Assembly Utilities and Commerce Committee                       
          (14-0)

                                       POSITIONS
           
           Sponsor:
           
          Author

           Support:
           
          California Public Utilities Commission
          Coalition of California Utility Employees
          Independent Energy Producers Association
          Pacific Gas and Electric Company











           Oppose:
           
          None on file
          



          Lawrence Lingbloom 
          AB 57 Analysis
          Hearing Date:  May 21, 2002