BILL ANALYSIS                                                                                                                                                                                                    



                                                                       


           ------------------------------------------------------------ 
          |SENATE RULES COMMITTEE            |                    AB 8X|
          |Office of Senate Floor Analyses   |                         |
          |1020 N Street, Suite 524          |                         |
          |(916) 445-6614         Fax: (916) |                         |
          |327-4478                          |                         |
           ------------------------------------------------------------ 
           
                                         
                                 THIRD READING


          Bill No:  AB 8X
          Author:   Keeley (D), et al
          Amended:  3/22/01 in Senate
          Vote:     27 - Urgency

           
          WITHOUT REFERENCE TO FILE

           SENATE APPROPRIATIONS COMMITTEE  :  8-2, 3/23/01
          AYES:  Alpert, Bowen, Burton, Escutia, Karnette, Murray,  
            Perata, Speier
          NOES:  McPherson, Poochigian

           SENATE FLOOR  :  27-9, 3/22/01
          AYES:  Alarcon, Alpert, Bowen, Brulte, Burton, Chesbro,  
            Costa, Dunn, Escutia, Figueroa, Johannessen, Karnette,  
            Kuehl, Murray, O'Connell, Ortiz, Peace, Perata, Polanco,  
            Romero, Scott, Sher, Soto, Speier, Torlakson,  
            Vasconcellos, Vincent
          NOES:  Ackerman, Haynes, Knight, Margett, McClintock,  
            Monteith, Morrow, Oller, Poochigian

           ASSEMBLY FLOOR  :  Not relevant


           SUBJECT  :    Electric power

           SOURCE  :     Author


           DIGEST  :    This bill makes changes in the following areas:   
          (1) qualifying facilities, (2) Department of Water  
          Resources Power Purchasing Program and (3) San Diego  
          ratepayers.
                                                           CONTINUED





                                                                 AB 8X
                                                                Page  
          2


          NOTE:   Senate amendments  delete the prior version.  As it  
          left the Assembly, the bill was authored by Migden and  
          expanded the authority of the Electricity Oversight Board.

           ANALYSIS  :    This bill consists of three main components:

           Qualifying Facilities
           
          Current law requires the California Public Utilities  
          Commission (CPUC) to establish energy payments for  
          qualifying facilities (QFs) based on formulas which reflect  
          the spot market price of natural gas sold at the California  
          border.

          Current law allows energy payments to QFs to be based on  
          prices paid by the Power Exchange (PX) under certain  
          circumstances.

          This bill repeals those provisions and instead requires the  
          CPUC to set payments to QFs consistent with federal law and  
          regulation.

           Department of Water Resources (DWR) Power Purchasing  
          Program

           Current law establishes a process for DWR to buy  
          electricity and sell it directly to customers using the  
          investor-owned utilities (IOUs) as billing and collection  
          agents.  In connection with such purchases and sales, DWR  
          is authorized to issue bonds in compliance with a statutory  
          formula.

          This bill clarifies that as a matter of existing law, DWR  
          is entitled to be paid for the electricity it sells to  
          customers at a rate equal to the generation component of  
          electric rate.

          This bill specifies that the state can issue a maximum of   
          $10 billion worth of bonds to finance the purchase of  
          electricity.  It replaces the statutory formula (specified  
          in AB 1X) with language that sets a specific cap of $10  
          billion.








                                                                 AB 8X
                                                                Page  
          3

          This bill makes other clarifying and technical changes to  
          the DWR electricity purchase and sales program.

           San Diego Ratepayers

           Current law requires the CPUC to establish a rate ceiling  
          of $0.065/kilowatt-hour for the energy portion of electric  
          bills for residential, small and medium commercial (less  
          than 100 kilowatts), and street lighting customers of San  
          Diego Gas and Electric Company (SDG&E).  

          This bill requires the CPUC to extend a rate freeze of  
          $0.065/kwh, subject to adjustment by the CPUC, for the  
          energy portion of electric bills on the energy sold by  
          SDG&E to all commercial customers.  This freeze is applied  
          retroactively to February 7, 2001 and will last only until  
          the rate freeze for Southern California Edison (SCE) and  
          Pacific Gas & Electric Company (PG&E) ends.

           Background
           
           QFs
           
          In 1978, Congress and the President enacted the Public  
          Utility Regulatory Policies Act  (PURPA) which encouraged  
          competition in the power generation market through the  
          creation of non-utility power producers known as qualifying  
          facilities (QFs).  

          To accomplish this, PURPA required the utilities to  
          purchase power from the QFs and to pay those QFs based on  
          the utilities' "avoided cost" - the cost that the utility  
          would otherwise pay to generate or procure power - not on  
          the QF's actual cost of producing power.  The cost of QF  
          power is then passed through to utility customers.  

          PURPA requires the electric utility to purchase the  
          electricity from the QFs at rates which "shall be just and  
          reasonable to the electric customers of the electric  
          utility and in the public interest."  Furthermore, the  
          rates charged cannot exceed the utility's avoided cost.

          "Avoided cost" is determined by the CPUC and has been  
          computed based on a formula which estimated the cost of  







                                                                 AB 8X
                                                                Page  
          4

          running an additional gas-fired powerplant. When  
          California's electric market was restructured in 1996, the  
          method, but not the formula, for determining avoided cost  
          was set in statute.  AB 1890 (Brulte), Chapter 854,  
          Statutes of 1996, established an avoided cost methodology  
          based on competitive prices as established through the PX.   
          AB 1890 also created an alternative methodology for avoided  
          cost which relies on the spot market price of natural gas  
          at the California border.  Just as over-reliance on spot  
          market prices in times of shortage led to volatile and high  
          electricity prices for power bought through the PX, so too  
          has this reliance on spot market natural gas prices lead to  
          high prices for power purchased from QFs.

           DWR Power Purchasing Program
           
          In early February 2001, DWR stepped in to temporarily  
          assume the utilities' role of buying power when the  
          utilities' were no longer financially capable of entering  
          into power purchase contracts.  AB 1X (Keeley), Chapter 4,  
          Statutes of 2001, established a process for DWR to assume  
          that role and created a direct relationship between DWR and  
          the customer - the utility was charged only with providing  
          billing and collection services. The vast majority of DWR's  
          purchases have been funded via loans from the state's  
          General Fund, and PG&E and SCE have not remitted any monies  
          back to DWR for its purchases.

          DWR intends to finance its purchases through the sale of  
          bonds and levelize charges to its customers to ensure those  
          bonds will be repaid.  That financing has been delayed  
          because of uncertainties in the legislation and,  
          apparently, challenges to the CPUC decisions implementing  
          that legislation.  This bill attempts to clear up some of  
          that ambiguity in order to facilitate the financing process  
          and ensure the monies advanced from the General Fund will  
          be paid back.

           San Diego Ratepayers
           
          Earlier this year, the Senate passed SB 43X (Alpert), a  
          bill which extended a rate cap to large electricity  
          customers in San Diego that was modeled on the rate cap  
          enjoyed by large customers in SCE and PG&E service  







                                                                 AB 8X
                                                                Page  
          5

          territories.  This bill is very similar to SB 43X, though  
          the bill is modified to reflect the fact that DWR is now  
          purchasing electricity on behalf of SDG&E. 

           Comments
           
           QFs
           
          Overhauling Public Utilities Code Section 390 is necessary  
          because it needlessly limits the flexibility of the CPUC,  
          requires the CPUC to set QF prices based on costly spot  
          market natural gas prices, and relies on a PX which is  
          bankrupt.  By replacing the existing Section 390 with a  
          provision requiring the CPUC to follow federal law, this  
          bill provides the CPUC with the maximum flexibility to set  
          QF prices consistent with the public interest.  The CPUC  
          has issued a proposed draft decision which establishes  
          energy prices for QFs and requires SCE and PG&E to pay the  
          QFs on a going-forward basis.

           DWR Power Purchasing Program

           These provisions reflect changes which the Treasurer, the  
          Department of Finance, and the staff of the CPUC believe  
          are necessary to ensure the state's taxpayers, through DWR,  
          receive immediate and continuing payment for power sold to  
          retail customers.  These changes are also necessary to  
          facilitate the ability to obtain interim financing and bond  
          financing for DWR's purchases.  DWR is spending, on  
          average, between $40 million and $50 million a day to buy  
          electricity on behalf of California ratepayers and the  
          proceeds from this financing will repay money borrowed from  
          the General Fund.  

           FISCAL EFFECT  :    Appropriation:  No   Fiscal Com.:  Yes    
          Local:  Yes


          NC:sl  3/23/01   Senate Floor Analyses 

                       SUPPORT/OPPOSITION:  NONE RECEIVED

                                ****  END  ****